Skip to content
Delta Structures
EstimateFree estimate
KNOWLEDGE HUB · 112 FREE FIELD GUIDES

Know before you build.

Plain-language guides from our engineering desk. No jargon without a translation and no scare tactics, just the checks and rules of thumb professionals use on site, so you can talk to any contractor, including us, as an informed client.

You have read 0 of 112 guides
DID YOU KNOW15 OF 36

Differential settlement, not settlement itself, is what cracks buildings – the problem is uneven movement.

FROM THE GUIDE Structural crack vs shrinkage crack

Showing 12 of 112 guidesAll 112 guides

No guides match “”.Try a broader word such as damp, cement or RERA, or ask Delta below.
DID YOU KNOW · 1 OF 210

Rust expands 4-6 times the steel it grows from - that expansion is what pops the concrete off old Kolkata buildings.

These guides describe standard Indian construction practice and field checks aligned with IS codes, such as IS 456 for concrete, IS 383 for aggregates and IS 1893 for seismic zoning. They are general education. Every building is different, so treat anything structural as a reason for an on-site professional assessment, not a do-it-yourself diagnosis.

ASK DELTA · ENGLISH · বাংলা · हिंदी

Still have a question?

Ask in English, Bengali or Hindi. Answers come from these guides, with the source named.

Ready to plan your own build?

Five taps give you a cost range, a season plan and your area’s rules. Or send us your plot for a free preliminary estimate, usually within 48 hours.*

*Indicative, not guaranteed. Timing varies with the complexity of your query.

Search or ask Delta
ENGINEERING· 15 MIN READ
এই গাইডটি এখনও শুধু ইংরেজিতে।

Building plan sanction in Kolkata (KMC): steps, papers and certificates

The Kolkata Municipal Corporation building at Esplanade
Photo: Sudipta Mallick, CC BY 2.0, via Wikimedia Commons
THE SHORT ANSWER

Inside the Kolkata Municipal Corporation, you can’t build, extend or structurally alter a building without a Building Permit from the Municipal Commissioner. A licensed building surveyor or architect files your plan online; KMC lists every defect at once within 15 days and decides within 60 days of a valid application. The permit lasts at least 5 years (renewable to 10), you give notice when you start, at plinth level and when you finish, and nobody may move in until KMC issues the completion certificate.

IN PLAIN WORDS

The permit is like a reserved train ticket: it names the train, the coach and the berth. The notices along the way are the ticket checks, and the completion certificate is the exit gate. Change trains without telling anyone and the ticket stops counting.

Every new building, every added floor and every change to the structure of a building inside the Kolkata Municipal Corporation needs a Building Permit. The rules behind it are the Kolkata Municipal Corporation Act, 1980 and the KMC Building Rules, 2009. They are detailed, and they are enforced at three points that matter to an owner: when the permit is issued, during construction through the notices, and at the end through the completion certificate, without which the building cannot be lawfully occupied or connected to KMC's water and drains.

This guide first explains why the sanction matters beyond the permit itself, what to settle before anyone draws, how long the process really takes, why files come back, how to work with your licensed building surveyor or architect, which papers to keep, and what a flat buyer should ask to see. The sections after that set out the rules step by step, with their rule numbers. KMC Building Rules in our Lab gives a first answer on how much your plot allows.

Why the sanction matters beyond the permit

A building's papers follow it for its whole life. Banks ask for the sanctioned plan and the completion certificate before a home loan or a loan against property; buyers' lawyers ask for them before a sale; KMC asks for them before water and drain connections; and since January 2025 KMC has said that neither a KMC water connection nor a CESC power connection is to be given to a new building without a completion certificate. A building that does not match its sanction can face a demolition order under section 400 of the KMC Act, and that risk passes to whoever owns it.

The sanction also protects the people in the building. The plan is checked for open spaces, light and air, staircases, fire escape routes and structural responsibility, and the professionals who sign it carry legal responsibility for the safety of the structure.

Settle these before anyone draws

  • Title: a registered deed in the owner's name, mutation done, and boundaries that match the deed. Gaps here are the most common reason a file stalls.
  • Tax: property tax and any other KMC dues paid up to the last quarter.
  • The road: its width in front of the plot as KMC records it, because height, floor area and open spaces all follow from it. A road that looks wide on the ground can be narrower on record, or the reverse.
  • A strip for road widening: whether KMC's regular line or the rules ask for a strip of land to be gifted, which changes the usable plot.
  • Clearances: land conversion, heritage, trees, airport height, fire safety and others, which KMC wants in hand before the plan is filed. Our guide to clearances on top of the sanction lists them.
  • The soil: a soil report is required above 10 m and we advise one for every plot, because Kolkata's soft clay decides the foundation.
  • What you want to build: the number of floors, flats, parking and the use, so the plan is drawn once for what the plot allows.

How long it really takes

The rules set clear limits: KMC sends one requisition listing all defects within 15 days, you answer within 15 days, and KMC decides within 60 days of a valid application, with the larger plans going through the Municipal Building Committee. A complete, correct file for a house can move within these limits. In practice the time depends mostly on what happens before filing: a title with gaps, a missing clearance or a plan drawn before the road width was checked can add months.

Plan the whole project with this in mind. The months spent on title, mutation and clearances are usually longer than the months KMC takes. Our Sanction Navigator lists the steps for your kind of building, and our Construction Timeline Phaser shows where the approval months fall in the whole build.

Why files come back

Most of these are avoidable with a careful check before filing. Because the rules give one chance to answer the requisition, answering it completely matters as much as the first filing.

  • The area in the deed does not match the measured plot, or the boundaries are unclear.
  • Mutation is not complete, or tax dues are outstanding.
  • Open spaces, ground coverage or height do not match what the road width allows.
  • Parking, staircase widths or the lift do not meet the rules for the size of the building.
  • A required clearance or no objection certificate is missing.
  • Declarations, undertakings or the indemnity bond for a deep foundation are incomplete.
  • Drawings and the statement of areas disagree with each other.

Working with your LBS or architect

The licensed building surveyor, architect and engineers who sign the plan are named in the application, file it online and give the notices during construction. Under the rules they are jointly and severally responsible for the safety of the structure. Choose people licensed or empanelled for your building's height and foundation, check their names on KMC's lists, and agree in writing what they will do: the plan, the structural design, the soil report, the online filing, the answers to requisitions, the notices and the supervision.

Keep them involved through the build. A plinth notice, a drain inspection or a completion notice filed late or not at all can hold up the completion certificate at the end, when the family or the buyers are waiting to move in.

The papers to keep

  • The Building Permit and the sanctioned plan, as issued electronically, with a printed set on site.
  • The notice of commencement and its acknowledgement.
  • The plinth notice, KMC's inspection and any directions given.
  • Any notice of internal change, or the revised sanction for anything outside the sanctioned area.
  • The structural stability certificate, the drainage, fire, electrical and lift certificates where they apply.
  • The completion certificate, and any partial certificate for a part of the building.
  • The soil report, structural drawings and the as-built drawings, which help with any future repair or addition.

Small plots and older colonies

Many plots in Kolkata are small, irregular or on narrow lanes, especially in older colonies and on former thika land. In March 2025 KMC announced relaxations for owners of small plots in colonies and on thika land, with foundations supervised by KMC-empanelled structural engineers, and the state published draft amendments to the rules in April 2025 and notified them in September 2025. Rules for small plots are changing, so we check the text in force for your plot before anything is drawn.

Gouri Bari Lane, one of the narrow old lanes of North Kolkata
Photo: Biswarup Ganguly, CC BY 3.0, via Wikimedia Commons

For a flat buyer in KMC

  • Ask for the Building Permit number and the sanctioned plan, and check that the building you see matches it: floors, open spaces, the position of your flat.
  • Ask for the completion certificate before taking possession; a flat offered without one is a risk.
  • Check that the project is registered with WBRERA if it should be, and that the registration number is on the certificate applications.
  • Look for the board on site with the permit number and the professionals' names during construction.
  • Ask a lawyer to check the title alongside the building papers.

Before anyone files: you, the plot and the papers

KMC takes an application from the owner, or from someone with the right to build, who holds the conveyance deed and the mutation certificate and owes no property tax or other municipal dues. The file has to show:

  • Your title: the registered deed, plus a registered deed of declaration of the boundaries if the deed doesn’t give them (rule 4(3) and 4(18)).
  • Tax paid up to the last quarter, with a declaration that nothing is due to KMC (rule 4(9)).
  • The key, site and building plans and the specifications: one set for a home on a plot of 500 m² or less, six sets for anything else (rule 4(2)).
  • KMC’s declarations, undertakings and indemnities (Schedules II to V), including an indemnity bond when there are piles, a deep foundation or a basement (rule 4(10) to 4(12)).
  • Any clearance your plot needs, which KMC wants before you apply: land conversion and mutation from the BL&LRO, an Urban Land Ceiling NOC (plots of 500 m² or more where that Act applies), KMC’s Environment and Heritage Department, tree-felling permission and any other NOC.
  • A registered gift deed, if a strip of land is being gifted to KMC to widen the road (rule 4(19)).

Who has to sign, by height

KMC decides who must plan, design and supervise by the height of the building and its foundation (rule 47), and these professionals are jointly and severally responsible for the safety of the structure. A Class II licensed building surveyor may sign buildings up to 10 m, a Class I up to 15.5 m (rule 50). KMC lists every licensed surveyor and empanelled engineer on its building pages.

A home up to 10 m, no deep foundationWHO YOU ENGAGE (RULE 47)At least a licensed building surveyor (LBS)SOIL REPORT (RULE 57)Not required, though we still advise one
10 m to 15.5 m, or any building with piles or a basementWHO YOU ENGAGE (RULE 47)An LBS or architect, with a structural engineerSOIL REPORT (RULE 57)Required above 10 m, from a geotechnical engineer
Above 15.5 mWHO YOU ENGAGE (RULE 47)An architect, a structural engineer, a geotechnical engineer and a structural reviewerSOIL REPORT (RULE 57)Required

From filing to the Building Permit

  1. 1Get any relaxation first. A plot on a narrow road under rule 59(2), or a request to treat another side as the back of the building, is decided before the plan goes online.
  2. 2Your LBS or architect files online on KMC’s building portal. They have 3 days from the first login to finish the entry, and 3 working days after the final submission to hand in the hard copies.
  3. 3Within 15 days KMC sends one requisition listing all the defects at once, and you have 15 days to answer it (rule 12). If the answer doesn’t come in time, the application lapses and has to be filed again.
  4. 4Any plan other than a home on a plot of 500 m² or less goes to the Municipal Building Committee, whose recommendation goes to the Mayor-in-Council (rule 38).
  5. 5KMC sanctions or refuses within 60 days of a valid application, or 30 days for some kinds of alteration (rule 13). If it doesn’t, you can make a representation to the Mayor, who must direct a decision within 30 days (rule 18).
  6. 6You pay the building permit fee, worked out on the sanctioned floor area (basement, covered parking and mezzanine included), the width of the road and the zone, at rates that differ by use (rules 41 and 42). KMC then issues the Building Permit and the sanctioned plan electronically.

While you build

  • The permit is valid for at least 5 years from the date of issue and can be renewed, for a fee, up to 10 years in all (rule 15).
  • Give KMC notice of commencement at least 7 days before work starts, and within 2 years of the permit (rule 22). The notices of commencement and completion can be filed online.
  • Keep a set of the sanctioned plans on site, with a board showing the premises number, the owner, the professionals’ names and the permit number and date (rule 23).
  • When the structure reaches plinth level (or 1 m above ground, if that’s higher), give notice: KMC inspects within 7 days and gives any directions within 3 days (rule 24). Drains are inspected before they are covered (rule 25).
  • No deviation from the plan. An internal change inside the sanctioned covered area needs 15 days’ written notice with your professionals’ certificate; anything outside it needs a revised sanction first (rule 26).
  • No building work between sunset and sunrise without KMC’s permission (rule 34).

Completion certificate, then moving in

  • Within one month of finishing, give notice of completion with the completion plans and a structural stability certificate and, where they apply, the drainage, fire safety, electricity and lift certificates (rule 27).
  • KMC inspects within 15 days and issues the completion certificate within 10 days of a satisfactory inspection (rule 28). If nothing comes within 30 days, you can make a representation to the Mayor (rule 31).
  • Without the certificate, KMC may not connect the building to its water mains or drains (rule 28(6)), and nobody may occupy it (rule 32). A partial or block-wise certificate can cover a finished part (rules 29 and 30).
  • After a Supreme Court order, KMC said in January 2025 that promoters must undertake to hand over flats only after the completion certificate, and that neither a KMC water connection nor a CESC power connection would be given without one.
  • Any later re-erection, addition or alteration needs a fresh application (rule 33).

Work that needs no permit

Rule 3(2) lists work you can do without a Building Permit: painting and whitewashing, re-flooring, plaster and patch work, a false ceiling, an internal door, window or ventilator, repairs to a staircase or lift shaft, replacing fallen bricks and repairing damaged pillars or beams (an engineer should still design that repair), renewing plumbing and sanitary lines, and repairing a boundary wall. A new internal partition wall, a parapet or chajja within the limits, and minor roof repairs need no permit either, but you give the Municipal Commissioner 15 days’ written notice first. Changing the structure of a damaged roof needs written permission, with plans and a stability certificate.

If something was built without sanction

KMC first serves a stop-work notice. It then decides the case under section 400(1) of the KMC Act after a hearing, where the structure may be demolished, partly demolished or kept, depending on how far the rules were broken and whether it is safe; where there is danger, it can demolish directly under section 400(8). Banks and buyers ask for the sanctioned plan and the completion certificate, so a deviation travels with the property.

Changes to these rules in 2025

The state published draft amendments to the KMC Building Rules on 7 April 2025 (UD&MA notification 272) and notified them on 4 September 2025, as the Millennium Post reported the next day: among them ground coverage of 60% on plots up to 500 sq m and 50% above, more floor area on some narrow roads, a higher FAR near metro lines, online filing on the Common Application Form and five years’ liability for the professionals who sign. The notified text was not online when we checked (17 Nov 2026), so this guide reads the draft for the changes. Before your plan is drawn, we check the text in force that day.

Questions people ask

Who can file a building plan in KMC?

A licensed building surveyor or architect files it online on the owner's behalf, with engineers as the height and foundation require. The owner must hold the title, the mutation and paid-up tax.

How long does KMC take to sanction a plan?

The rules give KMC 60 days from a valid application, after one requisition within 15 days. The months before filing, on title and clearances, often take longer.

Can you start work after filing, before the permit?

No. Work starts only after the Building Permit is issued, with notice of commencement given at least 7 days before.

What happens if you build something different from the plan?

Internal changes inside the sanctioned area need notice; anything outside it needs a revised sanction first. Unsanctioned work can lead to a stop-work notice and a demolition order under section 400.

Can you move in before the completion certificate?

No. The rules do not allow occupation, or KMC water and drain connections, without the completion certificate.

Can you handle the sanction for us?

Yes. We check what your plot allows before anything is drawn, the licensed professionals file it, and we follow it through every notice to the completion certificate.

RED FLAGS ON SITE
  • Work starting before the Building Permit and the sanctioned plan are in hand
  • No board on site naming the permit, the owner and the professionals
  • A covered setback, an extra room or an extra floor “to be regularised later”
  • Possession of a flat offered without a completion certificate
PRO TIP

Sanction liaison is one of our services. We work out what your plot allows before anything is drawn (FAR, height, open spaces, parking), the licensed professionals file it, and we follow it through every notice to the completion certificate. KMC Building Rules in our Lab gives you the first numbers in a minute.

TRY IT · FREE LAB TOOLKMC Building RulesHow much can you build on your plot in Kolkata?Open the tool →
QUIZ · THREE QUESTIONS

Did it stick?

QUESTION 1 OF 3 Who files your building plan with KMC?
Ask our engineers on WhatsApp
Sources · checked 14 Oct 2026
  1. KMC Building Rules, 2009, consolidated to 23 Dec 2019 (Indian Kanoon)Checked 14 Oct 2026
  2. KMC Building Rules, 2009, with amendments (kmcgov.in, PDF)Checked 14 Oct 2026
  3. KMC: building sanction (who may apply, demolition under section 400)Checked 14 Oct 2026
  4. KMC: online submission of building plans (instructions)Checked 14 Oct 2026
  5. KMC: user manual, sanction and CC/OC through the Common Application FormChecked 14 Oct 2026
  6. KMC: borough building officesChecked 4 Oct 2026
  7. Millennium Post: KMC to strictly enforce completion certificate rules (January 2025)Checked 14 Oct 2026
  8. UD&MA notification 272, 7 Apr 2025: draft amendments to the KMC Building Rules (PDF)Checked 17 Nov 2026
  9. Millennium Post, 5 Sept 2025: KMC caps building heights, fixes 5-yr liability for construction defects (the amendments notified)Checked 17 Nov 2026
  10. The Kolkata Municipal Corporation Building Rules, 2009, with amendments (kmcgov.in, PDF)Checked 14 Oct 2026
  11. KMC: building sanction (who may apply, demolition under section 400)Checked 14 Oct 2026
  12. Times of India, 8 March 2025: KMC relaxations for small plots in colonies and on thika land (via Bengal Info)Checked 15 Nov 2026
  13. UD&MA notification 272, 7 Apr 2025: draft amendments to the KMC Building Rules (PDF)Checked 15 Nov 2026
  14. Millennium Post, 5 Sept 2025: KMC caps building heights, fixes 5-yr liability for construction defects (the amendments notified)Checked 17 Nov 2026

Checked against these sources on the dates shown, pending our team’s sign-off. Rules change, so we check them again for your plot before anything is filed.