Differential settlement, not settlement itself, is what cracks buildings – the problem is uneven movement.
Thin (under 1mm), random or map-patterned, and only skin-deep in the plaster = shrinkage, usually cosmetic. Wide (3mm+), directional (diagonal from window corners, long horizontals, stepped through brick joints), passing through the wall, or growing over time = possibly structural — get it assessed.
No guides match “”.Try a broader word such as damp, cement or RERA, or ask Delta below.
DID YOU KNOW · 1 OF 210
Rust expands 4-6 times the steel it grows from - that expansion is what pops the concrete off old Kolkata buildings.
These guides describe standard Indian construction practice and field checks aligned with IS codes, such as IS 456 for concrete, IS 383 for aggregates and IS 1893 for seismic zoning. They are general education. Every building is different, so treat anything structural as a reason for an on-site professional assessment, not a do-it-yourself diagnosis.
ASK DELTA · ENGLISH · বাংলা · हिंदी
Still have a question?
Ask in English, Bengali or Hindi. Answers come from these guides, with the source named.
Ready to plan your own build?
Five taps give you a cost range, a season plan and your area’s rules. Or send us your plot for a free preliminary estimate, usually within 48 hours.*
Building plan sanction in a West Bengal municipality: e-Grihanaksha and the 2007 rules
The Nabadwip Municipality office in Nadia district, West BengalPhoto: Amitabha Gupta, CC BY 4.0, via Wikimedia Commons
THE SHORT ANSWER
In a municipality (Rajpur Sonarpur, Baranagar, Panihati, Serampore and the rest), the Board of Councillors issues the Building Permit under the West Bengal Municipal (Building) Rules, 2007, and you can file online through e-Grihanaksha. The site plan is approved first, then the building plan, which must be decided within 60 days. How high you can build depends on the width of the road in front (8 m on a lane of 2.4 to 3.5 m, 14.5 m on 7 to 10 m). The sanction lasts 3 years, renewable for 2, and nobody may move in before the occupancy certificate.
IN PLAIN WORDS
A municipality checks the ground before the house: first it approves the plot as a building site, then the building on it. It’s like getting the venue confirmed before you print the wedding cards.
Much of the Kolkata region outside the city itself is made up of municipalities: Rajpur Sonarpur and Baruipur in the south, Maheshtala and Budge Budge along the river, Baranagar, Kamarhati, the Dum Dums, Panihati and the towns up the Barrackpore line, Barasat and Madhyamgram to the north-east, and Uttarpara to Serampore across the Hooghly. All of them sanction building plans under the same state rules, the West Bengal Municipal (Building) Rules, 2007, made under the West Bengal Municipal Act, 1993.
This guide first explains how to confirm that your plot is under a municipality, how the online system works, why the road in front decides so much, what the rules ask of the ground, how long things take and what happens after the occupancy certificate. The sections after that set out the rules step by step, with their rule numbers, and list the municipalities on our area pages. Plot Potential in our Lab shows how much a plot allows, and Sanction Navigator lists the steps.
Confirm the body first
Municipal boundaries around Kolkata are not always where people expect. Parts of Garia are KMC wards while others are Rajpur Sonarpur; Garden Reach is KMC while Maheshtala next to it is a municipality; Salt Lake is a corporation while Lake Town beside it is South Dum Dum; Bally left Howrah corporation and became a municipality again in 2021; villages a short walk from a municipal town are under a gram panchayat; and Barrackpore Cantonment is not part of Barrackpore Municipality at all.
The surest check is the property tax bill or assessment, which names the body that taxes the plot, together with the deed's description of the property. If the plot has never been assessed, the municipality's ward map and the land records help. Getting this right first decides which rules, which office and which professionals apply.
The Bally Municipality building in Howrah: Bally left Howrah corporation and became a municipality again in 2021.Photo: Yogabrata Chakraborty, CC BY-SA 4.0, via Wikimedia Commons
e-Grihanaksha in practice
e-Grihanaksha is the state's single-window online system for building plan approval in municipalities. The licensed building surveyor or architect enters the application and uploads the drawings and papers; the site plan and then the building plan move through the municipality's scrutiny online, and the applicant can track the file. Requisitions, fees and the sanction come through the same route. Some municipalities still take applications at the counter as well.
The online system does not change what the rules ask for. A file with a gap in title, a missing clearance or a plan that breaks the height or coverage limits will still come back, only faster.
The road decides more than height
In the municipal rules, the width of the road or passage in front of the plot decides the maximum height, and with it how many floors are possible; it also affects the open spaces and parking. A new home needs a road or passage at least 2.4 m wide, and the height steps up as the road widens: 8 m on a lane of 2.4 to 3.5 m, 11 m up to 7 m, 14.5 m up to 10 m and so on.
Many plots in the municipal towns are on narrow lanes. The width that counts is the width on record and as measured, not the width the lane seems to have when cars are parked elsewhere. If part of the plot is to be gifted to widen the road, the plan can use the wider road, but the plot gets smaller. Measuring the road and checking its record is one of the first things we do.
What the rules ask of the ground
The site plan is approved before the building plan, and the municipality looks at the ground itself: whether the land record matches the building, whether the land is below the crown of the street, whether it can drain to a public drain and whether the soil can carry the building. A soil test report with the safe load on the soil goes with the papers. Land in a sinking zone needs the state's approval first, and no pond, canal, wetland or drain may be filled without the Board of Councillors' approval with the state's prior consent.
These checks matter in the low, soft ground around Kolkata. Many plots on the edges of the towns were once paddy fields, ponds or ditches, and a filled pond can go on settling for years. Our guides to soil testing, foundation types and land conversion explain what this means for the building.
How long it takes
The rules give the municipality 15 working days to ask for more information and 60 days from the building plan application, or from the information asked for, to decide. A requisition left unanswered for a month can mean refusal. For a house with clear title, a mutated plot and a plan that fits the road, these limits are realistic. Title gaps, land still recorded as agricultural, or a plan that has to be redrawn add months, and those are almost always settled before filing.
During construction
The notices are part of the approval, not paperwork to catch up on later. The commencement notice goes in before work starts, the plinth notice when the structure reaches plinth level, with the geotechnical engineer's certificate on the foundation, and the completion notice within a month of finishing. The sanctioned plans and a board with the permit number and the professionals' names stay on site. An internal change inside the sanctioned covered area needs notice; anything outside it needs a revised plan before it is built.
After the occupancy certificate
Water and drain connections from the municipality follow the certificate; without it they are not given.
The building is assessed for property tax; keep the assessment and pay from the first bill.
Mutation of flats to buyers, where flats are sold, follows the municipality's own procedure.
Any later addition or alteration needs a fresh application; the occupancy certificate covers the building as built, not future changes.
Keep the sanctioned plan, the certificates and the structural drawings together for future repairs, loans and sales.
Which rules apply
Most of our area pages outside Kolkata, Howrah and the planned townships fall under a municipality, governed by the West Bengal Municipal Act, 1993. Building plans there follow the West Bengal Municipal (Building) Rules, 2007, which apply to municipal areas, notified areas and industrial townships (rule 1). No one may build, rebuild, extend or alter a building without a Building Permit from the municipality’s Board of Councillors (rule 11). Applications can go in online through e-Grihanaksha, the state’s single-window building plan approval system, or at the municipality.
1The site plan is approved first (rule 4, Form A). You may file the building plan at the same time, at your own risk, but it is considered only after the site plan is approved.
2For the site, the municipality checks that the land record matches the building you propose, the land is not below the crown of the nearest street, it can drain into a public drain and the soil can carry the building (rule 3). Land in a sinking zone or a central business area needs the state’s approval first.
3Within 15 working days it may ask for more information, and a requisition left unanswered for a month can mean refusal (rules 5 and 6).
4Within 60 days of the building plan application, or of the information it asked for, the Board of Councillors sanctions it (Form C), sanctions it with conditions, gives a provisional sanction or refuses it (Form D) on the grounds in section 210 of the Act (rules 19 and 21).
5The permit is issued once the sanction fee is paid (rule 21). The fee is worked out on the total covered area, at a basic rate for your own home and at multiples of it for flats for sale and other uses (rule 24).
The papers
Form B with the declarations and indemnities the rules ask for, stamped as the Stamp Act requires, and copies of the documents that give you the exclusive right to build (rule 11(3)).
Tax receipts up to the last quarter and the municipality’s declaration that nothing is due.
The approved site plan, the soil test report with the safe load on the soil, and the names and consent of your technical team.
Two sets of the key plan, site plan, building plan and specifications at first, then four sets with the structural plan, design calculations and soil report before the sanction (rule 11(9)).
Where they apply: the NOCs and clearances your plot needs, an Urban Land Ceiling NOC for plots of 500 m² or more, a registered gift deed for land given to widen the road, an indemnity bond for piles, a deep foundation or a basement, and a registered boundary declaration if your deed doesn’t show the boundaries (rule 11(4), (6), (8) and (11)).
The licensed building surveyor, structural engineer and geotechnical engineer must be empanelled with that municipality (rule 14), and they are individually and collectively responsible for the safety of the structure and its foundation (rule 15).
Below 11.5 mWHO YOU ENGAGE (RULE 15)At least a licensed building surveyor (LBS)
11.5 m to 14.5 m, or with piles, a deep foundation or a basementWHO YOU ENGAGE (RULE 15)An LBS or architect, with a structural engineer
Above 14.5 mWHO YOU ENGAGE (RULE 15)An LBS or architect, a structural engineer and a geotechnical engineer
How high, and how much of the plot
A new home needs a road or passage at least 2.4 m wide, though a home up to 7 m may stand on a long-recorded passage of 1.2 m (rule 45). Ground coverage for homes runs from 65% on plots up to 200 sq m down to 50% above 500 sq m, and 40% for other uses (rule 46). Above 14.5 m a building counts as tall: it needs a structural safety certificate, and the municipality issues the permit only after the Superintending Engineer of the Municipal Engineering Directorate approves it (rule 53). The rules also provide for consulting the Director of Fire Services (rule 83).
2.4 m to 3.5 mMAXIMUM HEIGHT (RULE 49)8 m
Over 3.5 m to 7 mMAXIMUM HEIGHT (RULE 49)11 m
Over 7 m to 10 mMAXIMUM HEIGHT (RULE 49)14.5 m
Over 10 m to 15 mMAXIMUM HEIGHT (RULE 49)18 m
Over 15 m to 20 mMAXIMUM HEIGHT (RULE 49)24 m
Over 20 m to 24 mMAXIMUM HEIGHT (RULE 49)36 m
Over 24 mMAXIMUM HEIGHT (RULE 49)1.5 × (the road width + the front open space)
The sanction is valid for 3 years and can be renewed for 2 more; a partly built building with an occupancy certificate can be revalidated for 5 years (rule 23).
Give notice of commencement at least 7 days before work starts (rule 28, Form E), and keep the plans and a board with the permit number and the professionals’ names on site until the occupancy certificate.
At plinth level, or 1 m above ground if that’s higher, give notice (Form F): the municipality inspects within 15 days and gives any directions within 7 (rule 30). The geotechnical engineer certifies the foundation with this notice (rule 18).
An internal change inside the sanctioned covered area needs 15 days’ notice with drawings; anything outside it needs a revised plan first (rule 31).
No pond, canal, wetland or drain may be filled; only the Board of Councillors, with the state’s prior approval, can allow it (rule 8).
No building work between sunset and sunrise without permission (rule 29).
Completion and the occupancy certificate
Within a month of finishing, give notice of completion (Form G) under section 212 of the Act, with completion plans, the structural safety certificate and, where they apply, the drainage, fire safety, electricity and lift certificates (rule 33). A home or school up to 8 m on a plot of up to 200 sq m needs only a written intimation, except in Salt Lake.
The municipality inspects within 15 days and issues the occupancy certificate within 15 days of the inspection, once leftover building materials are cleared off the road (rule 34). A refusal must give reasons within 30 days; if nothing comes in 30 days you can make a representation to the Chairman, who has 30 days to decide (rule 35).
Without the certificate there is no municipal water or drain connection (rule 34), and nobody may occupy the building (rule 36). Any later addition or alteration needs a fresh application (rule 37).
Work that needs no permit
With prior intimation to the municipality, and with the owner responsible for the safety of the building and its neighbours, rule 11(2) exempts an internal partition wall, a parapet up to 1.5 m or a chajja up to 50 cm, repairs to a staircase, lift shaft or boundary wall, painting, re-flooring, rebuilding a damaged roof without changing it, a false ceiling, plaster and patch work, an internal door or window, replacing fallen bricks or repairing damaged pillars or beams (an engineer should still design that repair), and plumbing repairs.
Every one of them follows the 2007 rules. Where a body differs or a page needs a second check, we say so here.
Garia, Sonarpur and BaruipurMUNICIPALITIESRajpur Sonarpur, BaruipurWORTH KNOWINGRajpur Sonarpur sanctions homes up to 8 m directly; a relaxation goes to the Chairman and commercial plans to its Building Sub-committee. Parts of Garia are KMC wards.
Garden Reach, Maheshtala and Budge BudgeMUNICIPALITIESMaheshtala, Budge BudgeWORTH KNOWINGGarden Reach itself is KMC (Borough XV).
Bishnupur, Amtala and Diamond HarbourMUNICIPALITIESDiamond HarbourWORTH KNOWINGMost of the belt is under gram panchayats.
Baranagar, Sinthi and BelghariaMUNICIPALITIESBaranagar, Kamarhati, Dum Dum, North Dum DumWORTH KNOWINGNear the airport, so check the height first. Cossipore and Sinthi are KMC.
Salt Lake, Lake Town and Bangur AvenueMUNICIPALITIESSouth Dum DumWORTH KNOWINGLake Town, Bangur Avenue and Dum Dum Park; near the airport. Salt Lake itself is Bidhannagar Municipal Corporation.
Madhyamgram and BarasatMUNICIPALITIESBarasat, MadhyamgramWORTH KNOWINGThe villages around them are under gram panchayats.
Sodepur, Agarpara and KhardahMUNICIPALITIESPanihati, Khardaha, Titagarh, BarrackporeWORTH KNOWINGThe cantonment has its own board, not the municipality.
Howrah, Shibpur and SantragachiMUNICIPALITIESBally, UluberiaWORTH KNOWINGBally merged into Howrah Municipal Corporation in 2015 and has been a municipality again since 12 November 2021.
Hooghly riversideMUNICIPALITIESUttarpara-Kotrung, Konnagar, Rishra, Serampore, Baidyabati, DankuniWORTH KNOWINGChandannagar is a municipal corporation.
The Board of Councillors may order a building demolished or altered if it was started without sanction, departs from the sanctioned plan or breaks the rules, after giving the owner notice of a date and time for a hearing (rule 32). Demolished material must be cleared within 30 days.
Questions people ask
How do you know if your plot is in a municipality?
Check the property tax bill or assessment, which names the body, and the deed's description. If the plot has never been assessed, the ward map and land records help.
Can you apply online in a municipality?
Yes, through e-Grihanaksha, the state's single-window system. Your licensed building surveyor or architect files it; some municipalities still take paper applications too.
How many floors can you build on a narrow lane?
It depends on the width. On a lane of 2.4 to 3.5 m the rules allow 8 m, usually a ground floor and one more; wider roads allow more.
Is a soil test needed for a house in a municipality?
The rules ask for a soil test report with the safe load on the soil with the papers, and on the soft ground around Kolkata we advise one for every building.
How long is a municipal sanction valid?
Three years, renewable for two more; a partly built building with an occupancy certificate can be revalidated for five years.
Can you get the sanction for us in a municipality?
Yes. We check the plot against the 2007 rules before anything is drawn, and licensed professionals empanelled with your municipality file it and see it through to the occupancy certificate.
RED FLAGS ON SITE
A building plan treated as approved before the site plan is
A G+3 planned on a lane where the rules allow 8 m
A pond or ditch filled to make the plot
Water and drain connections promised before the occupancy certificate
PRO TIP
We check your plot against the 2007 rules (road width, height, coverage, open spaces) before anything is drawn, and the licensed professionals we work with, empanelled with your municipality, file it through e-Grihanaksha or at the counter. Sanction Navigator in our Lab lists your steps.
Checked against these sources on the dates shown, pending our team’s sign-off. Rules change, so we check them again for your plot before anything is filed.