Plain-language guides from our engineering desk. No jargon without a translation and no scare tactics, just the checks and rules of thumb professionals use on site, so you can talk to any contractor, including us, as an informed client.
You have read 0 of 112 guides
DID YOU KNOW15 OF 36
Differential settlement, not settlement itself, is what cracks buildings – the problem is uneven movement.
Thin (under 1mm), random or map-patterned, and only skin-deep in the plaster = shrinkage, usually cosmetic. Wide (3mm+), directional (diagonal from window corners, long horizontals, stepped through brick joints), passing through the wall, or growing over time = possibly structural — get it assessed.
No guides match “”.Try a broader word such as damp, cement or RERA, or ask Delta below.
DID YOU KNOW · 1 OF 210
Rust expands 4-6 times the steel it grows from - that expansion is what pops the concrete off old Kolkata buildings.
These guides describe standard Indian construction practice and field checks aligned with IS codes, such as IS 456 for concrete, IS 383 for aggregates and IS 1893 for seismic zoning. They are general education. Every building is different, so treat anything structural as a reason for an on-site professional assessment, not a do-it-yourself diagnosis.
ASK DELTA · ENGLISH · বাংলা · हिंदी
Still have a question?
Ask in English, Bengali or Hindi. Answers come from these guides, with the source named.
Ready to plan your own build?
Five taps give you a cost range, a season plan and your area’s rules. Or send us your plot for a free preliminary estimate, usually within 48 hours.*
Reading a schedule: baseline, critical path, float
A Gantt chart: tasks as bars against time, the start of reading a schedulePhoto: Bare Knuckles HC, CC0, via Wikimedia Commons
THE SHORT ANSWER
Baseline: the originally committed plan — the reference every update is compared against. Critical path: the chain of tasks where any delay directly delays handover. Float: the breathing room non-critical tasks have. If your contractor can't tell you what's on the critical path this month, nobody is actually steering the schedule.
IN PLAIN WORDS
A project is a relay race: the critical path is the slowest leg — speed up any other runner and the finish time doesn't change. Management means knowing, at all times, which leg is slowest.
Every building project has a date someone promised, and most of them miss it. Some delay is unavoidable: rain, a late approval, a material that does not arrive. What separates a project that recovers from one that drifts is whether anyone knows, week by week, which tasks actually decide the finish date and how much room the others have. That is what a schedule's baseline, critical path and float tell you.
This guide explains how a construction schedule is built, what the baseline is and why it must not quietly move, how to find the critical path, what float means, the cycle of a typical floor, what usually delays house projects in Kolkata, how to read a progress report, the decisions on your side that sit on the critical path, and what to do when the project slips. You do not need scheduling software to use any of it; you need the right questions.
How a schedule is built
A construction schedule starts as a list of activities: excavation, footings, plinth, each floor's columns and slab, brickwork, plaster, services, flooring and so on. Each activity has a duration, and most depend on others: the slab cannot be cast before its columns, the plaster cannot start before the conduits are in the walls, the tiles cannot go down before the waterproofing is tested. Linking the activities by these dependencies turns the list into a network.
Once the network exists, the schedule can be drawn as a bar chart, often called a Gantt chart, with a bar for each activity against the calendar. The bar chart is what most owners see. It is useful, but it hides the most important thing: which bars, if they slip, move the end date, and which can slip without consequence.
The baseline
The baseline is the schedule agreed at the start: the plan the contractor committed to and the reference every later update is compared against. It should be fixed and kept. A progress report that compares today's position with last month's revised plan, rather than with the baseline, can show a project on time month after month while the handover date drifts further away.
Changes to the baseline happen, but they should be explicit: a new baseline agreed in writing after a change in scope, a long approval delay or an agreed extension. Ask for every report to show the baseline dates and the current forecast side by side, with the difference in days.
The critical path
The critical path is the longest chain of dependent activities from start to finish. Because every activity on it depends on the one before, a delay to any of them delays the end date by the same amount. Activities off the critical path have some room to move without affecting the finish. Knowing which is which tells you where to focus attention, labour and money.
On a house, the critical path usually runs through the structure: excavation, foundations, plinth, and then each floor's columns, slab and curing in turn, because each floor must wait for the one below. Once the frame is up, the path often moves to the services and finishes on the last floors, or to a long-lead item such as a lift, the windows or a special stone. It can shift during the project, which is why it should be checked every few weeks, not just at the start.
Float
Float, or slack, is the time an activity can be delayed without delaying the end of the project. Activities on the critical path have no float. Others may have days or weeks: the boundary wall can usually be built any time before the finishes, and the order for wardrobe hardware can wait until the interiors begin. Float is a buffer, not spare time to be used up early. Once an activity has used its float, it joins the critical path, and the schedule has less room to absorb the next surprise.
The cycle of a floor
For a framed house, the time each floor takes is the heartbeat of the schedule. A typical floor cycle runs from setting out the columns to casting the slab, then waiting for the concrete to gain enough strength before the props are removed and the next floor can be loaded. The waiting is not wasted time: curing and the minimum times before removing formwork are set by IS 456 to protect the concrete, and cutting them short is how slabs crack and sag. Our guides to curing and to removing formwork explain why.
1Set out and fix the column steel, check it, and cast the columns.
2Erect the beam and slab formwork and props, and check them for level and strength.
3Fix the beam and slab steel, the conduits and the sleeves, and check them against the drawings.
4Cast the slab and beams in one continuous pour, and start curing at once.
5Cure for the days the specification sets, while starting the next floor's columns where the design allows.
6Remove the formwork and props only after the times IS 456 and the engineer set.
Workers guiding a concrete pump’s hose during a pourPhoto: WTF Formwork, CC BY-SA 3.0, via Wikimedia Commons
What usually delays house projects in Kolkata
Most delays on house projects come from a small set of causes, and many of them are predictable. A good schedule allows for them; a good manager watches for them.
The monsoon: excavation, foundations and roof work slow or stop in heavy rain, and curing and drying times stretch.
Festivals and harvest seasons, when much of the labour goes home for weeks.
Approvals and connections: the sanction, a revised plan, the water, drainage and power connections.
Long-lead materials and items ordered late: lifts, windows, special tiles and stone, sanitary fittings.
Decisions not made in time: tile and fitting choices, kitchen layouts, changes to rooms.
Payments late against the schedule, so labour and materials thin out.
Work redone after failed inspections or tests.
Reading a progress report
A useful progress report tells you where the project stands against the baseline, not just what happened. It should be short, regular and specific. If your reports read like a diary of activity, ask for these points instead.
The baseline finish date and the current forecast, and the difference in days.
The activities on the critical path now, and their status.
What was planned for the period and what was actually done.
Delays, their causes, and the recovery plan with dates.
Decisions and payments needed from you, with the dates they are needed by.
Dated photographs from the same positions each time.
The next period's plan: the look-ahead for the coming two to four weeks.
Your decisions are on the critical path too
Owners often think of the schedule as the contractor's problem, but many critical-path items are the owner's: approving drawings, choosing tiles and fittings, confirming the kitchen layout, releasing payments, and arranging access and connections. A tile choice made two weeks late can delay the flooring, and with it the handover, by two weeks. Ask the contractor for a decisions schedule, listing what you need to decide and by when, and treat it as part of the programme.
1Ask, every few weeks: what is on the critical path right now? A real answer names specific activities and dates.
2Ask: how does this week compare with the baseline? The answer should be days ahead or behind, with reasons.
3Ask: what do you need from us, and by when, to protect the date?
4Ask: what is the recovery plan for any delay, and what will it cost?
When the project slips
Slips are normal; unmanaged slips are not. When the forecast moves past the baseline, the first step is to find the cause and whether it is on the critical path. Then there are only a few ways to recover: work longer hours or more shifts on critical activities, add labour or equipment where it helps, change the sequence so that more activities run in parallel, or reduce or defer scope. Each has a cost and a risk, and some, such as cutting curing times, are not acceptable at all.
Agree any recovery plan in writing, with its dates and who pays for what. If the cause is on your side, such as a late decision or a change, expect the date to move and the contract to provide for it. If the cause is on the contractor's side, the contract's terms on delays and extensions apply. Our guides to the contractor agreement and to the warning signs of a stalling site cover what to do if the slip becomes a stall.
Three questions that expose schedule health
1'What's on the critical path right now?' — a real answer names specific tasks (e.g. 'second-floor slab; steel arrives Thursday').
2'How does this week compare to the baseline?' — days ahead/behind, with reasons, not vibes.
3'What decision do you need from ME to protect the date?' — client-side delays (tile selection, payments) are critical-path items too.
Questions people ask
What is the critical path in simple words?
The chain of tasks where any delay delays the handover. Speed up anything else and the finish date does not change.
What does float mean?
The time a task can slip without delaying the handover. Tasks on the critical path have none.
Why does each floor take weeks?
Because each slab must be cast, cured and gain strength before its props come out and the next floor loads it. IS 456 sets minimum times; cutting them risks cracked and sagging slabs.
Should the end date ever change?
Only by an explicit, written change to the baseline, for an agreed reason. A forecast that quietly moves every month is a warning sign.
How often should we get progress reports?
Weekly or fortnightly on a house, with the baseline, the forecast, the critical path, photographs and the decisions needed from you.
How do you schedule projects?
Our progress reports state the baseline against the actual position and the live critical path. Our Season Planner in the Lab shows how the time of year affects each stage.
RED FLAGS ON SITE
Schedule exists only in someone's head
End date unchanged for months while visible work slips
Updates describe activity ('work going on') instead of position ('slab 3 of 5 done, 4 days behind, recovery plan X')
PRO TIP
Our progress reports state baseline vs actual and the live critical path. It's the difference between reporting and managing.