DID YOU KNOW15 OF 36

Differential settlement, not settlement itself, is what cracks buildings – the problem is uneven movement.

FROM THE GUIDE Structural crack vs shrinkage crack

Showing 12 of 112 guidesAll 112 guides

No guides match “”.Try a broader word such as damp, cement or RERA, or ask Delta below.
DID YOU KNOW · 1 OF 210

Rust expands 4-6 times the steel it grows from - that expansion is what pops the concrete off old Kolkata buildings.

These guides describe standard Indian construction practice and field checks aligned with IS codes, such as IS 456 for concrete, IS 383 for aggregates and IS 1893 for seismic zoning. They are general education. Every building is different, so treat anything structural as a reason for an on-site professional assessment, not a do-it-yourself diagnosis.

ASK DELTA · ENGLISH · বাংলা · हिंदी

Still have a question?

Ask in English, Bengali or Hindi. Answers come from these guides, with the source named.

Ready to plan your own build?

Five taps give you a cost range, a season plan and your area’s rules. Or send us your plot for a free preliminary estimate, usually within 48 hours.*

*Indicative, not guaranteed. Timing varies with the complexity of your query.

Search or ask Delta
CIVIL WORKS· 12 MIN READ
এই গাইডটি এখনও শুধু ইংরেজিতে।

Why concrete needs 28 days (and daily water)

A worker keeps a freshly laid concrete pad wet with a hose so it cures
Photo: U.S. Navy, Public domain, via Wikimedia Commons
THE SHORT ANSWER

Concrete doesn't 'dry' — it hardens by a chemical reaction (hydration) that needs water. It reaches roughly two-thirds of its strength in 7 days and its full design strength at 28 days. Skipping the daily watering, or removing slab supports early, permanently weakens it.

IN PLAIN WORDS

Think of curing like proofing bread dough. Rushing the wait doesn't give you faster bread — it gives you worse bread. Concrete that isn't kept wet stops gaining strength, and there's no re-do later.

Concrete does not harden by drying. It hardens because cement reacts chemically with water, a process called hydration, and that reaction needs water to be present for days and weeks after the pour. Keeping the new concrete wet and at a reasonable temperature so the reaction can carry on is called curing. It is the cheapest quality step on any site and the one most often skipped.

This guide explains what happens inside concrete as it gains strength, why engineers talk about 28 days, what the Indian code asks for, how Kolkata's weather changes the picture, how long the formwork and props should stay, what skipped curing really costs you, and what you can check on your own site.

What happens inside the concrete

When water meets cement, the cement grains start to dissolve and form new compounds, chiefly calcium silicate hydrate, a gel that grows out from each grain and slowly fills the spaces between the sand and stone. That gel is what binds concrete together and gives it strength. The reaction also gives off heat, which is why a thick pour feels warm the next day.

Hydration is slow. In the first hours the concrete sets and loses its plasticity; over the next days and weeks the gel keeps growing and the pores keep shrinking, so the concrete becomes both stronger and less permeable. If the concrete dries out, the reaction slows and then stops in the dry zone. Water lost from the surface cannot be put back by watering later in the same way, because the pores that should have filled are already set in place.

Ordinary Portland cement (OPC) gains strength quickly in the first week. Portland pozzolana cement (PPC), the most common bag cement in eastern India, contains fly ash that reacts more slowly with the products of hydration; it gains strength more slowly at first and keeps gaining for longer, often well past 28 days, which is why it needs longer curing.

1 dayTYPICAL SHARE OF 28-DAY STRENGTH (OPC, MOIST-CURED, AROUND 27 °C)About 15 to 20%
3 daysTYPICAL SHARE OF 28-DAY STRENGTH (OPC, MOIST-CURED, AROUND 27 °C)About 40%
7 daysTYPICAL SHARE OF 28-DAY STRENGTH (OPC, MOIST-CURED, AROUND 27 °C)About 65 to 70%
14 daysTYPICAL SHARE OF 28-DAY STRENGTH (OPC, MOIST-CURED, AROUND 27 °C)About 90%
28 daysTYPICAL SHARE OF 28-DAY STRENGTH (OPC, MOIST-CURED, AROUND 27 °C)100% (the design figure)
90 days and beyondTYPICAL SHARE OF 28-DAY STRENGTH (OPC, MOIST-CURED, AROUND 27 °C)Often 10 to 20% more, especially with PPC

Why everyone talks about 28 days

Twenty-eight days is a convention, not a magic date. Concrete keeps gaining strength for months, but the industry needed one standard age at which to test and specify strength, and 28 days became that age around the world. In India, the grade of concrete (M20, M25 and so on) is its characteristic strength measured on 150 mm cubes at 28 days, under IS 456 and the test method in IS 516.

So when an engineer specifies M25, they mean cubes made from that concrete and cured in water should crush at an average comfortably above 25 N/mm² at 28 days, with very few results below it. The structure is designed around that number. If the concrete in your slab never reaches it because it was left to dry, the safety margins the engineer built in are quietly being used up.

What the Indian code asks for

IS 456, clause 13.5, sets the minimum. Exposed surfaces must be kept continuously damp or wet, by ponding or by covering with sacking, hessian, canvas or similar material kept constantly wet, for at least 7 days from the pour when ordinary Portland cement is used, and at least 10 days when blended cement (such as PPC) or mineral admixtures are used. In hot and dry weather the minimum is 10 days for OPC too, and for blended cements the code recommends extending curing to 14 days.

The code also allows curing compounds: liquid membranes sprayed on the surface that seal the water in. They are useful on vertical surfaces and where water is scarce, but they must be applied as soon as the surface water has gone, at the coverage the maker states, and they can stop later plaster or tiles bonding unless removed or chosen for that purpose.

PondingHOW IT WORKSLow bunds of lean mortar round the slab, filled with 25 to 50 mm of waterBEST FORRoof and floor slabs
Wet hessian or gunny bagsHOW IT WORKSWet sacking laid over or wrapped round the concrete and kept wetBEST FORColumns, beams, slabs in hot weather
Sprinkling or sprayingHOW IT WORKSRegular watering through the dayBEST FORSmall areas, when someone is on site all day
Plastic sheetHOW IT WORKSSheet laid tight over a wetted surface to stop evaporationBEST FORSlabs and pavements, with care at the edges
Curing compoundHOW IT WORKSSprayed membrane that seals the surfaceBEST FORVertical faces, places hard to keep wet

Kolkata weather and curing

Kolkata's climate makes curing both easier and harder. In the pre-monsoon months, April and May, afternoons are often around 35 to 38 °C with hot winds, and a freshly poured roof slab can lose water from its surface faster than the concrete bleeds it up. That is when plastic shrinkage cracks appear within hours of the pour, as fine, short cracks across the slab. Pouring early in the morning or late in the afternoon, shading and windbreaks, and covering the surface with wet hessian as soon as it can be touched without marking all help.

The monsoon brings rain, but rain is not curing. Concrete in a downpour is wet for an hour and then dries in the next sunny spell; heavy rain on a fresh slab can also wash cement out of the surface. Curing still has to be organised in the rainy months. In the dry, breezy winter months from November to February, humidity drops and surfaces dry quickly too, even though it is cooler.

High humidity for much of the year is a help: concrete in Kolkata dries more slowly than in a desert city. But it does not replace curing. The upper few centimetres of a slab, the part that protects the steel, are exactly the part that dries first.

Formwork and props: how long they stay

Curing and props are two different things, but they fail together on rushed sites. The shuttering under a slab and the vertical props holding it up carry the weight of the wet concrete until the concrete is strong enough to carry itself, and the concrete gets that strength only if it is cured. IS 456, clause 11.3, gives minimum stripping times for ordinary Portland cement in normal weather; with PPC or in cold weather they should be longer, and your engineer may set longer times for long spans or heavy loads.

Vertical formwork to columns, walls and beam sidesMINIMUM TIME AFTER THE POUR (OPC, NORMAL WEATHER)16 to 24 hours
Soffit formwork to slabs (props re-fixed at once)MINIMUM TIME AFTER THE POUR (OPC, NORMAL WEATHER)3 days
Soffit formwork to beams (props re-fixed at once)MINIMUM TIME AFTER THE POUR (OPC, NORMAL WEATHER)7 days
Props to slabs spanning up to 4.5 mMINIMUM TIME AFTER THE POUR (OPC, NORMAL WEATHER)7 days
Props to slabs spanning over 4.5 mMINIMUM TIME AFTER THE POUR (OPC, NORMAL WEATHER)14 days
Props to beams and arches spanning up to 6 mMINIMUM TIME AFTER THE POUR (OPC, NORMAL WEATHER)14 days
Props to beams and arches spanning over 6 mMINIMUM TIME AFTER THE POUR (OPC, NORMAL WEATHER)21 days
Timber props holding up slab formwork on a building site in the Gambia
Photo: Ikiwaner, CC BY-SA 3.0, via Wikimedia Commons

What skipped curing really costs

Concrete that is never kept moist can lose a large share of the strength it could have reached; tests reported over decades suggest that air-dried concrete may end up at well under three-quarters of the strength of the same concrete kept wet. The loss is worst at the surface, which is where it matters most for durability.

The cover concrete, the 20 to 50 mm between the steel and the air, is the building's defence against rust. Poorly cured cover is porous and full of fine cracks, so carbon dioxide and moisture reach the steel years earlier than they should. In Kolkata's humid air that is the start of the corrosion, spalling and rust-stained cracks that so many 30 and 40-year-old buildings show. Skipped curing also shows as dusty floors, surface crazing, plastic shrinkage cracks in slabs, and deflection where props went with the water.

Cube tests and what they do not tell you

On a properly run site, cubes are cast from the actual concrete at the pour, kept in a water tank and crushed at 7 and 28 days. IS 456, clause 15, sets how many samples to take: one sample (three cubes) for 1 to 5 m³ of concrete, two for 6 to 15 m³, three for 16 to 30 m³, four for 31 to 50 m³, and one more for every further 50 m³.

Cubes show the potential of the concrete that arrived, cured perfectly. They do not show what happened to the slab after the pour. A slab left dry in the sun can have cubes that pass comfortably while its own surface is weak and porous. That is why curing has to be checked on the slab itself, not just on the cube results.

Checking it on your own site

You do not need to be an engineer to see whether your concrete is being cured. A few minutes on site in the days after each pour tells you most of what you need to know, and asking about curing in writing before the pour sets the expectation.

  1. 1Before the pour, ask in writing: which cement is used, how the slab will be cured, for how many days, and when the props will come out.
  2. 2On the evening of the pour and the next morning, look for wet hessian, bunds and water on the slab. A dry, pale surface the day after is a warning.
  3. 3Visit at midday in the first week, when slabs dry fastest. Columns should be wrapped in wet hessian, not just splashed once.
  4. 4Look for fine plastic shrinkage cracks across a new slab within a day of the pour; report them early, as they can be closed while the concrete is fresh.
  5. 5Check that props are still in place under the slab and beams for the period your engineer gave; note the date any are removed.
  6. 6Ask for the cube results at 7 and 28 days, with the dates of casting, and keep them with your papers.

What to watch on your own site

  • Slabs and columns being watered (or kept covered with wet gunny bags / ponded water) every day for at least 7–14 days after casting.
  • Slab props (the vertical supports) staying in place for the period your engineer specifies — not removed in a few days to reuse them on the next job.
  • No heavy loading — brick stacks, machinery — on a fresh slab in the first weeks.

Why contractors cut this corner

Curing costs labour and ties up props with zero visible output — nothing 'new' gets built while it happens. That makes it the most silently skipped step in small projects. It's also invisible in the finished product until cracks and deflection show up years later.

Questions people ask

Can curing stop after 7 days?

For OPC concrete in mild weather, 7 days is the code's minimum. For PPC, which most homes in eastern India use, the minimum is 10 days and 14 is recommended, and in hot dry weather 10 days applies even to OPC. Longer curing never hurts and costs little more than a worker's time.

Does rain count as curing?

Not on its own. Rain wets the surface for a while and then it dries again in the sun; heavy rain on a very fresh slab can even wash cement out of the surface. Keep the ponding or wet hessian going through the monsoon too.

Do curing compounds work?

Yes, when applied on time and at the right coverage. They suit columns, walls and places that are hard to keep wet. Ask whether the compound will affect plaster or tiles that go on later; some need to be removed or are designed to be compatible.

When can brickwork start on a new slab?

Light work can usually start after the first week, but avoid stacking bricks, sand or cement in heaps on a young slab, and never before the props are allowed to come out. Concentrated loads on a slab that is still gaining strength cause cracks and sag. Your engineer should give the date.

Why did fine cracks appear on your slab the day after casting?

Most likely plastic shrinkage: the surface lost water faster than the concrete could bleed it up, usually on hot or windy days. They are often shallow, but they let water in. If seen while the concrete is fresh they can be closed by re-floating; later they are sealed. Better curing and early covering prevent them.

My contractor says PPC doesn't need curing. Is that true?

No. PPC needs longer curing than OPC, not less, because its fly ash reacts slowly and needs water for longer. The Indian code is explicit about this.

RED FLAGS ON SITE
  • Slab cast and left dry in the sun with no watering routine
  • Props removed within days to move to another site
  • Brick loads stacked on a slab less than 2 weeks old
PRO TIP

Ask your contractor one question: 'What is the curing plan and who does it daily?' If there's no clear answer, that's your answer.

TRY IT · FREE LAB TOOLConcrete LabGood concrete is chosen, mixed and cured.Open the tool →
PLAY · ONE MINUTEFact or myth?Ten things people say on sitePlay the game →
QUIZ · THREE QUESTIONS

Did it stick?

QUESTION 1 OF 3 How does concrete harden?
Ask our engineers on WhatsApp
Sources · checked 15 Nov 2026
  1. IS 456:2000 Plain and Reinforced Concrete, Code of Practice (cl. 11.3 stripping of formwork, 13.5 curing, 15 sampling)Checked 15 Nov 2026
  2. IS 516 Methods of Tests for Strength of ConcreteChecked 15 Nov 2026
  3. IS 1489 (Part 1):2015 Portland Pozzolana Cement, fly ash basedChecked 15 Nov 2026