Plain-language guides from our engineering desk. No jargon without a translation and no scare tactics, just the checks and rules of thumb professionals use on site, so you can talk to any contractor, including us, as an informed client.
You have read 0 of 112 guides
DID YOU KNOW15 OF 36
Differential settlement, not settlement itself, is what cracks buildings – the problem is uneven movement.
Thin (under 1mm), random or map-patterned, and only skin-deep in the plaster = shrinkage, usually cosmetic. Wide (3mm+), directional (diagonal from window corners, long horizontals, stepped through brick joints), passing through the wall, or growing over time = possibly structural — get it assessed.
No guides match “”.Try a broader word such as damp, cement or RERA, or ask Delta below.
DID YOU KNOW · 1 OF 210
Rust expands 4-6 times the steel it grows from - that expansion is what pops the concrete off old Kolkata buildings.
These guides describe standard Indian construction practice and field checks aligned with IS codes, such as IS 456 for concrete, IS 383 for aggregates and IS 1893 for seismic zoning. They are general education. Every building is different, so treat anything structural as a reason for an on-site professional assessment, not a do-it-yourself diagnosis.
ASK DELTA · ENGLISH · বাংলা · हिंदी
Still have a question?
Ask in English, Bengali or Hindi. Answers come from these guides, with the source named.
Ready to plan your own build?
Five taps give you a cost range, a season plan and your area’s rules. Or send us your plot for a free preliminary estimate, usually within 48 hours.*
How to read your sanctioned plan (FAR, setbacks, deviations)
A measured floor plan of a bungalow: the kind of drawing a sanction is checked againstPhoto: Ernest Geldart, CC0, via Wikimedia Commons
THE SHORT ANSWER
The sanctioned plan is the version of your building the municipality legally approved. Three things to understand on it: FAR/FSI (how much total floor area your plot is allowed), setbacks (mandatory open space you must leave on each side), and the golden rule — build what's drawn, because deviations invite penalties, regularization costs, or demolition orders.
IN PLAIN WORDS
Treat the sanction like a visa: it permits exactly what's stamped. Overstaying — an extra room here, a covered setback there — is easy to do and expensive to unwind.
The sanctioned plan is the set of drawings your municipality approved for your building. It is the legal description of what may stand on your plot: how big it may be, how tall, how far from each boundary, how it is used and what is left open. Everything later, from the completion certificate to a bank's loan and the sale of a flat, is checked against it. A building that matches its sanctioned plan is straightforward to complete, insure, mortgage and sell. One that does not can be stopped, fined, refused its certificate or, in serious cases, partly demolished.
This guide explains what a sanctioned plan contains, how to read its sheets, the planning numbers that shape it (floor area ratio, ground coverage, open spaces and height), what counts as a deviation, how changes are handled, and what to check on site as the building rises. The figures are from the KMC Building Rules, 2009 for Kolkata; other municipalities in West Bengal follow the West Bengal Municipal Building Rules, which use the same ideas with their own tables. It is general education: the exact figures for your plot come from the rules in force and your own plan.
What the sanction is, and what it is not
A building permit, or sanction, is the municipality's approval of a specific set of drawings for a specific plot, on the basis of the documents and the professionals' certificates filed with it. It confirms that the design, as drawn, follows the building rules. It is valid for a fixed period: under the KMC Building Rules, at least five years, renewable up to ten; in the municipalities under the state rules, three years, renewable for two.
The sanction does not check the quality of the construction, the structural design in detail, or the ownership of the land; those rest on the professionals and the owner, and on other papers. It also does not cover anything not shown on the drawings. An extra room on the roof, a covered balcony or a shop on the ground floor that the plan does not show is not sanctioned, however small it seems.
The sheets in a sanctioned plan
A sanctioned plan is usually a set of large drawing sheets bearing the municipality's stamp, the sanction or building permit number and date, and the signatures of the professionals on record. Ask for a full stamped copy, and keep a set on site throughout the work; the rules require the plans and a board showing the permit number to be kept on site.
Location and site plan: the plot, its boundaries and dimensions, the road in front and its width, north point, and the building's footprint with the open spaces on each side.
Floor plans: each floor's walls, rooms and their uses, doors, windows, stairs, lifts and shafts, with dimensions.
Sections: cuts through the building showing floor heights, the total height, the plinth, the parapet and the roof structures.
Elevations: the outside faces of the building.
Area statement: the plot area, the covered area on each floor, the total floor area counted for FAR, the ground coverage, parking and the figures allowed by the rules.
Notes and conditions: anything the municipality added, such as a strip of land to be gifted for road widening, conditions on drainage or trees, or the professionals' undertakings.
Floor area ratio: how much you may build
The floor area ratio, or FAR (also called floor space index, FSI), is the total floor area that may be built on all floors together, divided by the area of the plot. An FAR of 1.75 on a plot of 200 square metres allows about 350 square metres of floor area in all, whether that is spread over two large floors or more smaller ones, as long as the other rules are met too.
In Kolkata, the KMC Building Rules link the FAR mainly to the width of the road or means of access in front of the plot and to the building's use. For residential buildings, the table in the rules runs from 1.25 on access 2.4 to 3.5 metres wide, through 1.75 on 3.5 to 7 metres and 2.00 on 7 to 9 metres, up to 3.00 on roads wider than 24 metres. Narrower access allows only small buildings on special terms. The rules also exclude some areas from the count, such as parking and certain service spaces, under conditions; the area statement on your plan shows what was counted and what was not.
Ground coverage, open spaces and height
Ground coverage is the share of the plot the building may cover at ground level. For residential buildings under the KMC rules it is 60 percent on plots up to 200 square metres, falling in a straight line to 50 percent on plots of 500 square metres and more, with lower figures for other uses and very large plots. It works together with the open spaces: the strips of land that must be left open between the building and each boundary.
The open spaces are set by the building's height. For a residential building up to 7 metres, the KMC rules ask for 1.2 metres at the front and each side and 2 metres at the rear; up to 10 metres, the rear grows to 3 metres; taller buildings need wider open spaces on every side. These strips keep light and air in the rooms, room for fire engines and ladders, and distance between neighbours. They are the part of the sanction most often built over later.
The height allowed depends, again, on the width of the road in front, with taller buildings allowed only on wider roads and, above certain heights, only with fire safety and other approvals. Height is measured from the average level of the street at the centre line, not from the plot, so a plot raised above the road does not gain extra height.
FAR / FSIWHAT IT CONTROLSThe total floor area on all floors togetherWHERE YOU FIND IT ON THE PLANThe area statement: floor area counted, and the FAR allowed and proposed
Ground coverageWHAT IT CONTROLSThe share of the plot the building covers at ground levelWHERE YOU FIND IT ON THE PLANThe area statement and the site plan's footprint
Open spaces (setbacks)WHAT IT CONTROLSThe distance from the building to each boundaryWHERE YOU FIND IT ON THE PLANThe site plan, dimensioned at the front, sides and rear
Height and floorsWHAT IT CONTROLSThe building's total height and the number of floorsWHERE YOU FIND IT ON THE PLANThe sections and elevations
UseWHAT IT CONTROLSWhat each floor and room may be used forWHERE YOU FIND IT ON THE PLANThe floor plans and the area statement
ParkingWHAT IT CONTROLSThe number and size of car spaces requiredWHERE YOU FIND IT ON THE PLANThe ground or stilt floor plan and the area statement
Reading the plan against the site
You do not need to be an engineer to check the main points of a sanctioned plan on site. A tape, the stamped copy and an hour every few weeks are enough to catch most deviations while they are still cheap to correct. Do it with your engineer or contractor so that any question is answered on the spot.
1Check the plot: the boundary dimensions on the site plan match the plot on the ground and your deed, and any strip to be gifted for the road has been left out.
2Check the setting out: before the foundation is cast, measure the distance from the marked building lines to each boundary against the open spaces on the plan.
3Check the plinth: at plinth level, measure the footprint and its distances to the boundaries again; this is when the municipality's plinth notice is given.
4Check each floor: compare the outer walls, the room layout, the stair and lift positions and the projections such as balconies and sunshades with the floor plan.
5Check the height: compare each floor height and the total height with the section, and make sure no floor or room on the roof is added that the plan does not show.
6Check the open spaces: keep them open; no rooms, sheds, covered parking or boundary-to-building roofs in them.
What counts as a deviation
A deviation is anything built differently from the sanctioned plan. Some are small and can be put right by a revised plan; others break the rules themselves and cannot be sanctioned at all. The difference matters, because a change that stays within the rules can usually be regularised with a fee and a revised plan, while one that breaks them, such as building over the open spaces or above the permitted FAR or height, may have to be removed.
The deviations we see most often are building into the open spaces, especially at the rear and with covered balconies; an extra floor or a room on the roof; balconies enclosed into rooms; a stilt parking floor turned into flats or shops; stairs or lifts moved; and changes of use, such as a residential ground floor used as a shop or office. Each can affect the FAR, the coverage, the fire safety or the parking, and each can hold up the completion certificate for the whole building.
Building into the front, side or rear open spaces.
An extra floor, or rooms and sheds on the roof, beyond the sanction.
Balconies or terraces enclosed into rooms.
Parking areas converted into flats, shops or storage.
A change of use that the plan does not allow.
Floor heights or the total height above what is shown.
The building placed differently on the plot from the site plan.
Changing the design during construction
Designs change, and the rules allow for it, but the change must be approved before it is built, not after. Under the state rules for municipalities, an internal change within the sanctioned covered area needs notice with drawings, and anything outside it needs a revised plan first. Under the KMC rules, any later addition or alteration needs a fresh application. In both, the safe course is the same: ask your engineer or architect whether the change needs approval, and if it does, file the revised plan and wait for it before building the change.
Keep every revision with its stamp and date, and make sure the drawings on site are the latest approved set. A building built partly to one set and partly to another is a common cause of delays at completion.
What happens if the building does not match
The KMC Act gives the Municipal Commissioner powers to stop unauthorised construction and to order the unauthorised parts removed, and the state's municipal law gives municipalities similar powers. Short of that, a building that does not match its plan cannot get its completion or occupancy certificate until the deviation is regularised or removed, and without the certificate it may not be occupied or connected to municipal water and drains. Banks may refuse loans on flats in it, and buyers may refuse to buy them.
Regularisation, where the rules allow it, means filing revised drawings of what was built, paying the fees and penalties set by the municipality, and having the change approved. It is slower and costs more than getting the change approved first, and it is not available for everything. Deviations that break the core limits on open space, FAR, height or safety are the hardest to resolve.
For flat buyers
If you are buying a flat, ask to see the sanctioned plan and check that the flat you are buying is on it, on the floor and in the position stated, with the rooms and area shown. Check the number of floors in the building against the sanction; a floor added beyond it puts every flat in the building at risk. For projects registered with the West Bengal Real Estate Regulatory Authority (WBRERA), the sanctioned plan is among the documents the promoter must upload and keep available. Our guides to RERA and to the completion and occupancy certificates explain the rest.
Your flat is shown on the sanctioned plan, on the floor and side stated.
The building's number of floors and height match the sanction.
Parking you are offered is shown as parking on the plan.
Any change since the first sanction has its own stamped revision.
The project's RERA registration shows the same plan.
The three numbers that matter
FAR / FSIPLAIN MEANINGFloor Area Ratio: total built area ÷ plot area allowed by rulesWHY YOU CAREDecides how many floors / how much area you can legally build
SetbackPLAIN MEANINGMinimum open strip between your building and each plot boundaryWHY YOU CARECovering it is the most common deviation — and the most visible one
Sanctioned height / floorsPLAIN MEANINGThe approved vertical envelopeWHY YOU CAREAn 'extra' floor without approval risks the whole building's papers
Owner's habit worth forming
Keep a copy of the sanctioned drawing on site and compare monthly: wall positions, openings, floor count. Catching a deviation at brickwork stage costs a day; catching it at completion costs a certificate.
Questions people ask
What is the difference between FAR and ground coverage?
FAR controls the total floor area on all floors together; ground coverage controls how much of the plot the building covers at ground level. A building can meet one and break the other, so the plan shows both.
Why does road width matter so much?
Because the road carries the building's traffic, services and fire engines. The KMC rules tie the FAR and the height mainly to the width of the road or access in front, so a wider road allows a larger, taller building on the same plot.
Can you cover the open space at the back for a store room?
Not without it becoming a deviation. The open spaces must stay open. A store or shed built in them can hold up the completion certificate and may have to be removed.
How long is a sanction valid?
Under the KMC Building Rules, at least five years, renewable up to ten. In the municipalities under the West Bengal Municipal Building Rules, three years, renewable for two. Check the date on your permit and renew before it lapses.
What is the gifted strip on our plan?
Where a road is narrower than the rules want, the plan may require a strip along the front of the plot to be given for road widening, often in return for a higher FAR or height. That strip is not yours to build on, and the open spaces are measured from the new boundary.
Can you check our plan or handle the sanction?
Yes. We read sanctioned plans with owners and buyers, and we handle sanction drawings and liaison as a service. Our KMC Building Rule tool in the Lab shows the main limits for a plot.
RED FLAGS ON SITE
Construction differing from the drawing 'to be adjusted later'
Setback area being roofed or walled
No copy of the sanctioned plan available on site
PRO TIP
We handle sanction liaison as a service — but even if you build with someone else, never let the site drift from the approved drawing without a formal revision.