Shuttering (Formwork) Estimator
Concrete volume → formwork area & plywood
Category: Steel & repair
What you enter
- Concrete volume (m³)
- Member type: Floor slab 125–150 mm (×7), Beam (×11), Column (×13), Raft / footing (×2.5)
An example
With the starting values (Concrete volume (m³): 10; Member type: Floor slab 125–150 mm (×7)), it gives:
- Formwork contact area: 70 m² (753 sq ft)
- 12 mm ply (8×4 ft, +10%): 26 sheets
Good to know
Shuttering is measured by the concrete surface it touches — the 'formwork ratio' varies by member. Film-faced ply reuses for 4–6 casts; props, battens and clamps are extra.
Sources
- IS 14687:1999 (formwork)
- Our site practice
Checked 7 Oct 2026, pending our team’s sign-off.
Read the guide
Free, instant and indicative: a starting point for our engineers’ estimate, not a substitute for one.