After the props come down — the 3 checks on a new slab
The day shuttering is removed is the day defects surface: sag (deflection), honeycombing, and cold-joint lines. Ten minutes with a straightedge, a torch and a coin tells you whether the pour was good — and whatever you find must be assessed before it's plastered over.
Deshuttering is the reveal of a cake tin. Whatever the surface shows — voids, cracks, slumps — was baked in on casting day; icing over it doesn't fix the cake.
The day the shuttering comes off a slab, a beam or a column is the day you see what the pour really produced. Every defect in the concrete is there to see for the first and last time: honeycombing, cold joints, sag, cracks, bulges and leaking joints in the formwork. A few days later, plaster and putty can cover all of it. Ten careful minutes with a straightedge, a torch and a hammer, before anyone starts finishing, tell you whether the concrete is sound.
This guide explains when shuttering may come off and why it must not be rushed, the order of striking and re-propping, the checks on a newly stripped slab, beam and column, what each defect means, which repairs are legitimate, and what to record. Our Concrete Lab shows how concrete is chosen, mixed and cured, our honeycombing guide explains voids, and our shuttering guide covers the formwork itself.
When shuttering may come off
Concrete gains strength over days and weeks. Formwork can be removed only when the concrete can carry its own weight and whatever load comes onto it, without cracking or sagging. IS 456 gives guide times for ordinary Portland cement concrete in normal conditions, in clause 11.3, and the engineer can adjust them for the cement, the weather and the loads.
| Formwork | Usual minimum time with OPC (IS 456) |
|---|---|
| Vertical faces of walls, columns and beams | 16 to 24 hours |
| Slab soffits, with props left under | 3 days |
| Beam soffits, with props left under | 7 days |
| Props under slabs spanning up to 4.5 m | 7 days |
| Props under slabs spanning over 4.5 m | 14 days |
| Props under beams spanning up to 6 m | 14 days |
| Props under beams spanning over 6 m | 21 days |
These times are for OPC in normal weather. PPC, slag cement, cold weather or heavy loads from the floor above need longer; the engineer decides. Never take the props out from under a slab just because the shuttering boards above them are needed elsewhere.
Striking in the right order
- Remove side shutters of beams and columns first, carefully, without levering against the fresh concrete.
- Leave props under slabs and beams for the full time, or replace them at once with re-props where the boards are struck early.
- Strike from mid-span towards the supports, so the slab or beam takes its load gradually.
- Never strike under a slab that already carries fresh concrete, bricks or materials from the floor above.
- Keep props in line from floor to floor where several floors are propped, so loads pass straight down.
Checks on a stripped slab
- Look along the underside against a string line or a laser line: a visible sag at mid-span needs the engineer's check now, not after plastering.
- Look at the underside with a torch held low, so its light rakes across the surface: honeycombing, voids and rough patches show as shadows.
- Tap the surface with a hammer or a coin over a grid: a hollow sound marks a void or a thin skin over poor concrete.
- Look for lines across the slab where one batch stopped and the next began; a dark or rough line can be a cold joint.
- Look for cracks: their pattern, width and direction, and whether they run through.
- Look at the edges and around openings and pipes, where compaction is hardest.
- Look for exposed steel or cover blocks showing, which mean the cover is short there.
Checks on beams and columns
- The bottom of every beam and the ends near the columns, where steel is most congested and voids are most common.
- The foot of every column, where cement slurry leaks out of poorly sealed shutters and leaves stones.
- The joint where a column meets the beams, which is hard to compact and critical in an earthquake.
- Straightness and plumb: columns out of plumb or beams bowed beyond the tolerances the specification allows.
- Bulges where the shuttering moved during the pour.
- Sizes: a quick tape check against the drawing.
What each defect means
| What you see | Likely cause | What it needs |
|---|---|---|
| Sag at mid-span | Props struck early, formwork too weak, overload | The engineer's check before anything else |
| Honeycombing | Poor compaction, stiff mix, slurry leak | Assessment; repair to depth by the right method |
| Hollow sound | Void or delaminated skin | Mapping and repair |
| Cold joint line | A delay between batches | Assessment for leaks and strength |
| Fine map cracks on the surface | Plastic shrinkage from early drying | Usually sealed; better curing next time |
| Cracks across a slab or beam | Early loading, settlement of props, shrinkage or overload | The engineer's assessment |
| Exposed steel or cover blocks | Short cover, displaced steel | Repair with the right cover restored |
Curing after striking
Removing the shuttering exposes concrete that was protected until then, and it starts losing water at once, especially in Kolkata's summer heat and wind. Curing has to continue: IS 456 asks for exposed concrete to be kept moist for at least 7 days with ordinary Portland cement and at least 10 days with blended cements such as PPC and slag cement, longer in hot, dry weather. Slab tops are usually ponded or covered with wet hessian; columns and beam sides are wrapped in wet hessian or sprayed several times a day, or sealed with a curing compound.
The days after striking are also when loads arrive: bricks stacked on the new slab, scaffolding for the next floor, a mixer and its materials. Keep heavy stacks near the supports, not at mid-span, and spread them. Concrete still gaining strength can crack under a concentrated load that it would carry easily a month later. Our curing guide explains why the water matters.
Legitimate repairs, and what is not
Shallow surface defects are cut back to sound concrete with square edges, cleaned, wetted and repaired with a polymer-modified repair mortar or a flowable micro-concrete, then cured. Deeper defects, voids near or around the steel, and any defect in a column, at a beam-column joint or at the bottom of a beam near a support need the engineer's assessment and a designed repair; our honeycombing guide explains them.
What is not a repair is a smear of rich cement mortar over a void the same afternoon, a skim of plaster, or a coat of putty. They hide the defect from the owner and the engineer, and leave it open to water underneath.
If anyone starts patching, plastering or putting cement wash on newly stripped concrete before you or the engineer have looked, stop the work and ask why.
What to record
- The date of the pour and the date of striking for each member.
- Photographs of every slab soffit, beam and column after striking, with a scale and the member's mark.
- The defects found, marked on a sketch or the drawing.
- The engineer's decision on each defect, and the repair done.
- The test cube results for the pour.
- The props left in and the date each was removed.
The three checks
- Sight along the slab soffit (underside) against a level line: a visible sag at mid-span, or props re-inserted 'just in case', needs an engineer's deflection check now.
- Torch-light the surface at a low angle for honeycombing — exposed aggregate pockets, especially at beam bottoms and column heads where concrete is hardest to compact.
- Tap suspicious patches with a coin: a hollow click over a dense thud maps a void or delaminated skin.
What repair is legitimate
Small surface honeycombs are cut back to sound concrete and repaired with polymer-modified or free-flow grout — a defined engineering repair. What is not legitimate is a smear of rich cement mortar over the void the same afternoon. If reinforcement is visible in the void, stop and call the engineer; that is a structural repair, not a patch.
Questions people ask
How long should slab props stay in?
Under IS 456 for OPC in normal weather, at least 7 days for slabs spanning up to 4.5 m and 14 days for longer spans, with the boards allowed off after 3 days only if the props stay. Slower cements and cold weather need longer.
Can shuttering be removed early to use it on the next floor?
The boards can come off early only if props stay under the slab or re-props go in at once. The props themselves stay for the full time.
Is honeycombing on a new slab serious?
Shallow honeycombing can be repaired; deep voids, voids around the steel and voids in columns, joints or beam ends need the engineer's assessment.
What does a hollow sound mean?
A void or a thin skin over poor concrete under the surface. Map the hollow area and have it assessed before plaster goes on.
Why does a new slab sag?
Props struck too early, formwork that moved, or loads put on it too soon. A visible sag needs an engineer's check before finishing work continues.
Should the slab be plastered straight after striking?
No. Inspect and record it first, have any defects assessed and repaired, and let the curing finish.
Red flags
- Plastering crews starting the day after deshuttering
- Cement-slurry 'makeup' applied over beam bottoms
- Props removed early from the largest spans first
Pro tip
A slab that visibly sags, cracks in parallel lines, or sounds hollow over large areas needs professional assessment before any finishing work continues.
Try it in our Lab: Concrete Lab
Sources
- IS 456:2000 Plain and Reinforced Concrete, Code of Practice (clause 11.3, stripping time) (checked 15 Nov 2026)
- IS 14687 Guidelines for Falsework for Concrete Structures (Bureau of Indian Standards) (checked 15 Nov 2026)
- CPWD Handbook on Repair and Rehabilitation of RCC Buildings (checked 15 Nov 2026)
Checked against these sources on the dates shown, pending our team’s sign-off.