The snag list — inspecting a flat before you accept possession
Possession day is your maximum leverage; the day after, you're a complaint ticket. Walk the flat with a checklist, list every defect in writing (the snag list), get the developer's signature with a rectification date, and only then sign the possession letter. Two hours of methodical checking beats two years of society WhatsApp groups.
Accepting possession without a snag list is like signing for a courier box that rattles. Once you've signed 'received in good condition', the argument is over before it starts.
The day a new flat or house is handed over is the day you have the most leverage you will ever have over the builder. Before you sign the possession letter, the builder wants your signature and the final payment. After it, every defect becomes a complaint in a queue. A methodical inspection, a written snag list and a date for each fix turn that leverage into a finished home.
This guide explains when and how to inspect, what to take, a room-by-room checklist, water and drainage, electrical, structure and finishes, the documents to collect, measuring the carpet area, how to record and send the snag list, and what RERA gives you after possession. Our Room Area Converter checks the carpet area against the agreement, and our retention and defects period guide covers defects after handover.
When and how to inspect
- Ask for an inspection before the possession letter is signed, in daylight, with the water and electricity connected.
- Allow two to three hours for a flat; more for a house.
- Go with someone else, ideally an engineer, so one checks while the other writes.
- Inspect empty, before furniture and boxes hide floors and walls.
- If the builder offers the possession letter before you have seen the flat, ask to inspect first.
What to take
- The agreement, the floor plan and the specifications or finishes list.
- A tape measure or laser measure.
- A spirit level, or a level app on a phone.
- A coin or a small hammer for tapping tiles.
- A torch, for low-angle light on walls and floors.
- A phone charger or a small socket tester, for every socket.
- A bucket and a marble or small ball, for floor slopes.
- A notebook or the snag list on a phone, and masking tape to mark defects.
Water and drainage
- Run every tap for a few minutes, hot and cold; check the pressure and look under every sink and basin for drips.
- Flush every WC twice; watch it refill and stop cleanly, and check the base for leaks.
- Pour a bucket of water on each bathroom and balcony floor: it should run to the trap and drain, with no pools.
- Check every floor trap drains quickly and has a water seal, with no sewer smell.
- Run the shower and look at the joint between floor and wall.
- Look at the ceiling below the bathrooms where you can, and the walls behind them, for damp marks.
- Check the water storage, the pump if it is yours, and the meter.
Electrical
- Test every socket with a charger or tester.
- Switch every light and fan on and off, and try two-way switches from both ends.
- Switch on several heavy loads at once and check nothing trips.
- Press the test button of each residual current device; it should trip.
- Check the distribution board is labelled and closes properly.
- Check the AC points, geyser points and the bell or video door phone.
- Ask for the electrical contractor's test report.
Structure and finishes
- Tap every floor and wall tile with a coin: a hollow sound means the tile is not fully bedded.
- Look along walls against the window light for waves and patches; check corners with the level.
- Look for cracks in walls and ceilings, especially at corners of doors and windows and where walls meet beams; note their width.
- Check the floor slopes with the ball and the level, especially in bathrooms and balconies.
- Open, close and lock every door and window twice; check they do not stick, sag or rattle, and that the locks and handles work.
- Check window seals and the joint between the frame and the wall for gaps.
- Check the paint for patches, drips and uneven colour.
- Check the kitchen counter, the sink, the cabinets and their hardware.
- Check balcony railings for height and firmness.
- Look at the common areas: the stair, the lift, the parking, the roof, the water tanks.
Documents to collect
- The completion certificate and the occupancy certificate, or certified copies, for the building or block; our CC and OC guide explains them.
- The possession letter, with the date.
- The electrical test report and the lift certificates for the building.
- Warranty cards and manuals for the fittings, appliances and waterproofing.
- The as-built plan of the flat, with the services marked if available.
- The maintenance and association papers, and what has been paid.
- Receipts for every payment.
Measuring the carpet area
Under RERA, the flat is sold by carpet area: the net usable floor area within the walls, excluding the external walls, service shafts, the exclusive balcony or verandah and the exclusive open terrace, but including the internal partition walls, as section 2(k) of the Act defines. Measure a few rooms wall to wall, add them up with the internal walls and compare with the agreement. Our Room Area Converter works it out, and our guide to carpet, built-up and super built-up area explains the terms. If the carpet area is less than agreed, raise it in writing before signing.
The snag list
- Write each defect with its room, location, what is wrong, and a photograph.
- Mark the defects on site with small pieces of masking tape so the builder's team can find them.
- Give the list to the builder in writing, by email, the same day, and ask for a written date to fix each item.
- Re-inspect when they say the work is done, and tick off each item.
- Sign the possession letter with the open items listed on it, or only after they are fixed, as you agree.
- Keep the list, the photographs and the replies with your papers.
Signing a possession letter that says the flat was received in good condition, with no list of defects, weakens every later claim. Write the open items on it.
After possession: what RERA gives you
Under section 14(3) of the Real Estate (Regulation and Development) Act, 2016, if you bring a structural defect, or any other defect in workmanship, quality or provision of services, to the promoter's notice within five years of handing over possession, the promoter must fix it without further charge within thirty days. If not, you are entitled to compensation under the Act, and can complain to the West Bengal Real Estate Regulatory Authority.
That right works best for defects you can show were reported. Keep reporting new defects in writing, with photographs and dates, as they appear, especially after the first monsoon.
The two-hour checklist
- Water: run every tap 5 minutes, flush every WC twice, look under sinks; fill and drain the bathrooms and watch the floor traps actually drain (pooling = wrong slope).
- Electrical: carry a phone charger and test every socket; switch on everything at once and check the MCB doesn't nuisance-trip.
- Surfaces: coin-tap tiles for hollows, sight walls against window light for undulation, open-close every door and window twice and lock each.
- Documents: completion/occupancy certificate copy, electrical test report, warranty cards, and the carpet-area measurement against the agreement — measure two rooms yourself.
Paper the process
Email the snag list the same day so there's a dated record, and photograph every listed defect. Under RERA, the developer's defect liability for structural and workmanship defects runs five years from possession — but that lever only works for defects you can prove existed and were reported.
Questions people ask
Should the flat be inspected before signing the possession letter?
Yes. Before you sign is when the builder is most willing to fix things. Inspect, list the defects in writing and agree dates.
How long does a snag inspection take?
Two to three hours for a flat, more for a house. Go in daylight, with water and power connected.
What if the builder refuses an inspection before possession?
Ask in writing. If they still refuse, write the defects you find on the possession letter or send them in writing the same day, and keep a copy.
What is carpet area under RERA?
The net usable floor area within the walls, excluding external walls, shafts, exclusive balconies and terraces, but including internal partition walls (section 2(k) of the Act).
How long is the builder responsible for defects?
Under RERA section 14(3), for structural and workmanship defects reported within five years of possession, to be fixed within thirty days without charge.
Can you hire someone to inspect the flat?
Yes. An engineer or an inspection firm can do it more thoroughly. We carry out handover inspections and write the snag list for you.
Red flags
- Possession letter presented for signature before you've seen the flat
- Verbal promises to 'fix everything after you move in'
- No completion/occupancy certificate available on request
Pro tip
For a high-value purchase, a professional snagging inspection (an engineer with a moisture meter, level and socket tester) costs little against the defects it converts from your problem to the developer's.
Try it in our Lab: Room Area Converter
Sources
- The Real Estate (Regulation and Development) Act, 2016, sections 2(k) and 14 (India Code) (checked 15 Nov 2026)
- West Bengal Real Estate Regulatory Authority (checked 15 Nov 2026)
- The Kolkata Municipal Corporation Building Rules, 2009 (completion and occupancy, rule 27) (checked 15 Nov 2026)
Checked against these sources on the dates shown, pending our team’s sign-off.