Retention money & the defect liability period — your post-handover leverage

Two contract terms that protect you after the work is 'done'. Retention money is a small percentage (commonly about 5%) of each payment that you hold back and release only after a set period, so the contractor has a reason to come back and fix problems. The Defect Liability Period (DLP) is that agreed window after handover (often 6-12 months) during which the contractor must repair defects at their cost. Together they keep the contractor accountable when problems surface later — which, with construction, they do.

It's like keeping the last slice of a two-part payment until the tailor has fixed the hem after you've worn the suit a few times. Hand over every rupee on day one and you've given away your only leverage the moment a defect appears in month three.

The handover of a new house or a renovated flat is not the end of the contractor's job. Many defects in building work show themselves only after the owner moves in: a leak in the first monsoon, a crack as the walls dry out, a door that sags, a tile that sounds hollow, a drain that backs up. Two clauses in the agreement decide whether the contractor comes back to fix them: the defects liability period, and the retention money that secures it.

This guide explains what each clause does and how they work together, typical periods and figures and how to set them, what counts as a defect, how to run the period from handover to final release, the special case of buying a flat under RERA, what to do when a contractor does not return, and the warning signs. Our contractor agreement guide covers the rest of the agreement.

Two clauses, one purpose

The defects liability period, or DLP, is an agreed time after handover during which the contractor must repair defects in their work, at their own cost, when told about them in writing. Retention money is a small share of each payment that the owner holds back, so that the contractor has money waiting at the end of that period and a reason to return.

One without the other is weak. A defects period with nothing held back depends on the contractor's goodwill. Retention with no defined period leaves both sides arguing about when it is due. Together, they turn after handover from a hope into an obligation.

Typical figures

These are common patterns, not fixed rules. Public works use their own figures in their contract conditions. Agree yours in writing before work starts, not at handover.

TermCommon practiceNotes
RetentionAbout 5 percent of each paymentHeld from each running bill until a set total is reached, or throughout
Defects liability periodTwelve months from handover, for a houseLonger can be agreed for waterproofing and similar work
ReleaseHalf at handover, half at the end of the period, or all at the endReleased only after the listed defects are fixed
Security instead of cashA bank guarantee for the retention amountLets the contractor keep the cash while you keep the security

Why the defects period matters

Building work fails late in particular ways. Waterproofing is only proved by a monsoon. Plaster and masonry crack as they dry and shrink over the first months. Concrete continues to settle and shrink. Hardware loosens with use. Drains and traps show their faults under daily use. A twelve-month period after handover covers a full cycle of Kolkata's seasons, including one monsoon, which is when many of these show.

Some items deserve a longer period: roof and bathroom waterproofing, where many specialist firms give their own written warranties of several years, and the structural frame, where a defect may take longer to show. Where a supplier gives a warranty, ask for it in the owner's name and keep the card.

What counts as a defect

  • Work not done to the drawings, specifications or the agreed standard.
  • Leaks through roofs, terraces, bathrooms, walls, windows and pipes.
  • Cracks beyond the fine shrinkage cracks that are normal as new work dries, especially cracks that grow.
  • Hollow, loose or cracked tiles, and floors out of level.
  • Doors and windows that stick, sag or do not lock; hardware that fails.
  • Drains, traps and pipes that block, smell or leak.
  • Electrical faults in the contractor's wiring and fittings.
  • Not defects: damage from misuse, changes made by others, normal wear, and items the owner supplied unless they were fixed badly.
Floor tiles cracked and lifting
Floor tiles cracked and lifting. Photo: Mk2010, CC BY-SA 4.0, via Wikimedia Commons

Running the period, step by step

  1. At handover, walk through the building with the contractor and agree a snag list of everything unfinished or faulty, with a date to fix each one.
  2. Record the handover date in writing: the defects period starts from it.
  3. Keep a defects log as you live in the building: what, where, when first seen, with dated photographs.
  4. Report each defect to the contractor in writing, by email or message, as soon as you find it, and keep their reply.
  5. Give the contractor reasonable access to fix it, and check the repair when it is done.
  6. A month or so before the period ends, walk through the building again, ideally after the monsoon, and send the contractor a final defects list.
  7. Release the retention only when every listed defect is fixed, against a written note from both sides.

When the contractor does not return

If a defect is reported in writing and the contractor does not come back within a reasonable time, the agreement should allow you to have it repaired by someone else and recover the cost from the retention. Write to the contractor first, giving a final date and saying that you will do this. Keep the quotes, the bills and photographs of the defect and the repair.

If the cost of the repairs is more than the retention, the balance is a claim under the agreement and the general law of contract; the dispute clause in your agreement, such as mediation and then arbitration, sets the route. This is why the retention should be large enough to matter, and why it should never be released early.

Buying a new flat under RERA

If you buy a flat from a promoter rather than build, a different rule protects you. Under section 14(3) of the Real Estate (Regulation and Development) Act, 2016, if you bring a structural defect, or any other defect in workmanship, quality or provision of services, to the promoter's notice within five years of handing over possession, the promoter must fix it without further charge within thirty days. If they fail, you are entitled to compensation under the Act.

Report defects to the promoter in writing, with photographs and the date, and keep their reply. If they do not act, you can complain to the West Bengal Real Estate Regulatory Authority. Our RERA guide explains the Act.

Writing it into the agreement

  • The retention percentage, how it is deducted, any cap, and when and how it is released.
  • Whether a bank guarantee can replace cash retention.
  • The length of the defects liability period, from the date of handover, and any longer periods for waterproofing or other items.
  • What counts as a defect, and what does not.
  • How defects are reported, how soon the contractor must respond and repair, and what happens if they do not.
  • That suppliers' and specialists' warranties are passed to the owner.

Warning signs

  • An agreement with no retention and no defects period.
  • Pressure to release all the retention at handover, before a monsoon has tested the work.
  • A defects period that starts at an earlier date than handover, such as the completion of the structure.
  • Defects raised only by phone, with nothing in writing.
  • A contractor who asks for the retention to be paid early in return for finishing the last items.
  • Waterproofing warranties promised but never handed over.

We build a defects period and retention into our agreements as a matter of course, and we come back. A contractor who resists both clauses is telling you how they plan to treat problems after handover.

How to set it up

  • Write both into the contract: the retention percentage, and the DLP length and what it covers.
  • Release retention only after the DLP ends and outstanding defects are fixed — not at handover.
  • Keep a defects list during the DLP (leaks, cracks, hardware failures) and raise them in writing while you still hold retention.

Why it matters most on the things that fail late

Many defects — damp, settlement cracks, waterproofing failures, hardware sagging — only appear weeks or months after handover. Retention and a DLP are exactly what turn 'the contractor has vanished' into 'the contractor has a reason to return'.

Questions people ask

How much retention should you hold?

About 5 percent of each payment is common for building work. Agree the figure and how it is released in the agreement before work starts.

How long should the defects liability period be?

For a house, twelve months from handover is common, so that a monsoon passes inside it. Longer periods can be agreed for waterproofing.

When should the retention be released?

Only after the defects period ends and every defect reported during it has been fixed. Some agreements release half at handover and half at the end.

What if the contractor does not come back to fix a defect?

Write giving a final date, then have it repaired by someone else and recover the cost from the retention, as the agreement allows. Keep every message, quote and photograph.

Does RERA give flat buyers a defects period?

Yes. Section 14(3) of the RERA Act makes the promoter fix structural and workmanship defects reported within five years of possession, without charge, within thirty days.

Are hairline cracks in new plaster a defect?

Fine shrinkage cracks are common as new plaster dries and are usually filled before the final paint. Cracks that are wide, grow or follow a pattern should be logged and checked.

Red flags

  • A contract with no retention clause or defect liability period
  • Pressure to release the full retention at handover
  • No written record of defects raised during the DLP

Pro tip

Retention and a defect liability period are standard professional practice that protect you precisely when problems surface. We build both into our agreements as a matter of course — and honour them.

Sources

  1. The Real Estate (Regulation and Development) Act, 2016, section 14 (India Code) (checked 15 Nov 2026)
  2. West Bengal Real Estate Regulatory Authority (checked 15 Nov 2026)
  3. CPWD Works Manual (security deposit, defects liability) (checked 15 Nov 2026)
  4. The Indian Contract Act, 1872, and The Arbitration and Conciliation Act, 1996 (India Code) (checked 15 Nov 2026)

Checked against these sources on the dates shown, pending our team’s sign-off.

Skip to content
KNOWLEDGE HUB · {{ nAll }} FREE FIELD GUIDES

Know before you build.

Plain-language guides from our engineering desk. No jargon without a translation and no scare tactics, just the checks and rules of thumb professionals use on site, so you can talk to any contractor, including us, as an informed client.

{{ readLine }}

{{ countTxt }}

Loading the guides
We couldn’t load the guides.The connection may have dropped. Try again, or ask Delta below: its answers come from the same guides.
No guides match “{{ q }}”.Try a broader word such as damp, cement or RERA, or ask Delta below.
DID YOU KNOW · {{ factNo }}

{{ fact }}

These guides describe standard Indian construction practice and field checks aligned with IS codes, such as IS 456 for concrete, IS 383 for aggregates and IS 1893 for seismic zoning. They are general education. Every building is different, so treat anything structural as a reason for an on-site professional assessment, not a do-it-yourself diagnosis.

Ready to plan your own build?

Five taps give you a cost range, a season plan and your area’s rules. Or send us your plot for a free preliminary estimate, usually within 48 hours.*

Start your free estimate →Plan your build in five tapsTalk on WhatsApp

*Indicative, not guaranteed. Timing varies with the complexity of your query.

{{ g.dom }}· {{ g.mins }} MIN READ
{{ g.trNote }}

{{ g.title }}

{{ g.imgAlt }}
Photo: {{ g.imgBy }}, {{ g.imgLic }}, via Wikimedia Commons
THE SHORT ANSWER

{{ s.t }}{{ s.t }}

IN PLAIN WORDS

{{ s.t }}{{ s.t }}

{{ g.dNote }}

{{ s.t }}{{ s.t }}

{{ x.h }}

{{ s.t }}{{ s.t }}

  • {{ s.t }}{{ s.t }}
  1. {{ st.n }}{{ s.t }}{{ s.t }}
{{ r.label }}{{ c.k }}{{ c.v }}
{{ fg.alt }}
Photo: {{ fg.by }}, {{ fg.lic }}, via Wikimedia Commons

{{ x.h }}

{{ s.t }}{{ s.t }}

  • {{ s.t }}{{ s.t }}
  1. {{ st.n }}{{ s.t }}{{ s.t }}
{{ r.label }}{{ c.k }}{{ c.v }}

{{ g.faqT }}

{{ f.q }}

{{ s.t }}{{ s.t }}

RED FLAGS ON SITE
  • {{ s.t }}{{ s.t }}
PRO TIP

{{ s.t }}{{ s.t }}

SEEING THIS AT HOME?{{ g.probT }}Tick what you see and we tell you what it most likely means, with the fixes ranked honestly.Check yours → {{ g.goKick }}{{ g.goName }}{{ g.goDesc }}{{ g.goCta }} PLAY · ONE MINUTE{{ g.playName }}{{ g.playLine }}Play the game →
Ask our engineers on WhatsApp
{{ g.srcHead }}
  1. {{ s.l }}{{ s.chk }}

Checked against these sources on the dates shown, pending our team’s sign-off. Rules change, so we check them again for your plot before anything is filed.