Construction Timeline Phaser
Area + floors → indicative weeks per phase
Category: Engineering
What you enter
- Built-up area (sq ft)
- Floors (incl. ground)
An example
With the starting values (Built-up area (sq ft): 1500; Floors (incl. ground): 2), it gives:
- Foundation & plinth: 5 weeks
- RCC structure (2 slabs): 8 weeks
- Masonry, plumbing & wiring: 8 weeks (overlaps)
- Finishes & handover: 10 weeks (overlaps)
- Total: ≈ 27 weeks (~6 months)
Good to know
Assumes steady funding, timely decisions and a normal slab cycle (~3–4 weeks per floor). Monsoon slows excavation and concreting; sanction delays and late finish selections (tiles, sanitaryware) stall projects more than the construction itself. Phase overlaps are already netted into the total.
Sources
- Our project records
Checked 7 Oct 2026, pending our team’s sign-off.
Read the guide
- Payment milestones that protect you
- Early warning signs of a stalling site
- The daily progress report — what a well-run site writes down every day
Free, instant and indicative: a starting point for our engineers’ estimate, not a substitute for one.