Delta Structures

Switchboard heights & socket counts — the electrical plan you'll live with

Sockets are the cheapest thing to add before plastering and the most annoying thing to lack forever after. Plan by activity, not by room: every bed side, every counter appliance, TV wall cluster, work-from-home desk. Standard heights: switches 1200mm, sockets 300mm (600mm in kitchens above counter, 1500mm for geyser/AC points).

Count sockets the way you count wardrobe hangers — by what you own and where you use it, not by a builder's per-room formula from 1995.

The number and position of sockets and switches is decided once, on electrical marking day, before the walls are plastered. After that, every missing socket means an extension cord across the floor, an adaptor stacked on an adaptor, or a groove cut through finished paint. It is the cheapest thing to get right during a build and one of the most annoying to live with when it is wrong.

This guide explains how to plan by what you do in each room rather than a fixed count, the room-by-room points that age well, heights and positions, dedicated circuits, data and future-proofing with empty conduits, kitchens and bathrooms, safety, and how to run electrical marking day. Our Electrical Load Estimator works out the load, and our wiring guide covers wire and breaker sizes.

Plan by what you do

A builder's standard layout gives each room a fixed number of points. Real homes are used differently: a bed with a phone, a lamp and a laptop on each side; a living room with a TV, a set-top box, a router, a soundbar and a lamp; a kitchen counter with half a dozen appliances; a corner that became an office in 2020 and stayed one. Plan by listing what will be plugged in where, then add a spare at each place.

Do it with the furniture layout drawn: where the beds, the sofa, the TV, the desk and the kitchen appliances will be. Sockets behind a wardrobe, or a switch behind a door that opens over it, come from marking the points before the furniture was decided.

Room by room

RoomPoints that age well
BedroomTwo sockets each side of the bed; a TV point with three or four sockets and data; one general socket; an AC point on its own circuit; two-way switching for the main light from the door and the bed
Living roomA TV wall with four to six sockets and an empty conduit for cables; a socket near each seating corner for lamps and chargers; the router's place with power and data
KitchenSix to eight sockets above the counter; dedicated points for the chimney, hob, microwave or oven, fridge and water purifier
BathroomA geyser point on its own circuit, switched outside or high; a socket for a shaver or dryer away from water; an exhaust fan point
Study or work cornerFour sockets and a data point at desk height
Balcony and terraceA weatherproof socket for washing machines, cleaning or lights
Entrance and corridorsSwitches at each end, a socket for cleaning, a point for a doorbell or video door phone

Heights and positions

  • Switches about 1,200 mm above the finished floor, beside the door on the latch side, so they are found in the dark.
  • General sockets about 300 mm above the floor in living rooms and bedrooms.
  • Kitchen sockets above the counter, usually 150 to 200 mm above it, away from the sink and the hob.
  • Bedside sockets just above the bedside table, not hidden behind it.
  • TV sockets at the height of the TV's back or behind the cabinet, with conduit to the set-top box.
  • Geyser and AC points high, near the unit, as their makers suggest.
  • Measure from the finished floor level, agreed before marking, not the rough slab.

Dedicated circuits

Heavy appliances should each have their own circuit from the distribution board, with a wire and breaker sized for it: every air-conditioner, every geyser, the induction hob or oven, the washing machine and the water pump. A kitchen should have its own socket circuits, separate from the rest of the house. Dedicated circuits stop one appliance tripping everything else and keep each wire within its load. Our wiring guide lists the usual sizes.

Round-pin plugs of the BS 546 family that Indian plugs grew from (United Kingdom): the big 15 A pins are for heavy appliances, the 5 A for lighter ones.
Round-pin plugs of the BS 546 family that Indian plugs grew from (United Kingdom): the big 15 A pins are for heavy appliances, the 5 A for lighter ones.. Photo: Andrew Morgan, Public domain, via Wikimedia Commons

Data and future-proofing

Homes now need data as much as power: a router in a central place, wired points for the TV and the desk, cameras at the gate, a video door phone. Run data cables in their own conduits, apart from power cables, to the main places.

Where you are not sure, lay an empty conduit with a draw wire between two boxes and fit a blank plate. Pulling a wire through later takes minutes. Typical places are the TV wall to the cabinet, the ceiling for a future projector or fan, the balcony for lights, and the gate for a camera.

Empty conduit with a draw wire costs very little before plaster and saves cutting a finished wall later.

Kitchens and bathrooms

  • Kitchen sockets above the counter, not below near the sink, and none within easy splash of the sink.
  • Enough sockets for every appliance that stays plugged in, plus two spares for mixers and kettles.
  • Bathroom sockets and switches away from the shower and the bath, as the wiring code and the safety regulations set.
  • The geyser switch outside the bathroom, or high and away from water, with an indicator light.
  • Exhaust fans wired with a switch, or a timer that runs them for some minutes after use.

Safety

  • All socket circuits protected by a 30 mA residual current device, as the 2023 safety regulations require.
  • Every socket earthed; three-pin sockets wherever metal appliances are used.
  • Shuttered sockets in homes with small children.
  • No sockets in places that get wet: under sinks, outside without weatherproof covers, or on balcony floors.
  • No overloaded multi-plug adaptors as a permanent answer; add sockets instead.

Electrical marking day

  1. Have the furniture layout and the kitchen layout drawn and agreed.
  2. Walk each room with the electrician and the drawing, marking every switch, socket, light and data point on the wall at its height.
  3. Check each point against the list of what will be plugged in there.
  4. Mark the dedicated circuits and their appliances.
  5. Mark the empty conduits and where they run.
  6. Photograph every wall with its marks, and keep the photos as the record of where every conduit runs before plaster covers them.

Per-room minimums that age well

  • Bedroom: 2 socket points each bed side (phone + lamp), 1 TV cluster (3 sockets + data), 1 general, AC point with its own circuit.
  • Kitchen: 6–8 counter-height sockets minimum — chimney, hob ignition, fridge, microwave, mixer, kettle, water purifier, one spare.
  • Living: TV wall cluster of 4–6 with conduit for future cable/soundbar runs, plus one socket per seating corner.
  • Desk/WFH corner: 4 sockets + 1 data point; this is the most under-provisioned spot in post-2020 homes.

The conduit trick

Wherever you're unsure, have the electrician lay an empty conduit with a draw wire between two boxes and blank off the plate. Pulling a wire later through ready conduit is trivial; chasing a new wall groove through finished paint is demolition.

Questions people ask

How many sockets does a kitchen need?

Commonly six to eight above the counter, plus dedicated points for the chimney, hob, microwave or oven, fridge and water purifier.

What height should switches be?

About 1,200 mm above the finished floor, beside the door on the latch side.

Do ACs and geysers need separate circuits?

Yes. Each should have its own circuit from the board, sized for it, so it does not overload or trip other circuits.

Is it worth laying empty conduits?

Yes. Empty conduit with a draw wire, in the places you might need later, costs little before plaster and saves cutting walls afterwards.

Where should the Wi-Fi router go?

Somewhere central, high and open, with power and a wired data point, not in a cupboard at one end of the flat.

Can sockets be added after plastering?

Yes, by cutting grooves or with surface conduit, but it is messier and costs more. Planning them on marking day is far better.

Red flags

  • Whole rooms fed from one 2-socket board
  • Kitchen sockets below counter level near the sink line
  • No dedicated circuits for AC and geyser

Pro tip

Get the final furniture layout drawn before electrical marking day — the ₹0 decision that saves the most regret in interiors.

Work it out: Electrical Load Estimator

Sources

  1. IS 732 Code of Practice for Electrical Wiring Installations (Bureau of Indian Standards) (checked 15 Nov 2026)
  2. Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2023 (checked 15 Nov 2026)
  3. National Building Code of India 2016, Part 8 Building Services (Bureau of Indian Standards) (withdrawn by BIS on 30 April 2026; replaced by the National Building Construction Standards 2026, SP 7:2026) (checked 15 Nov 2026)

Checked against these sources on the dates shown, pending our team’s sign-off.

Skip to content
KNOWLEDGE HUB · {{ nAll }} FREE FIELD GUIDES

Know before you build.

Plain-language guides from our engineering desk. No jargon without a translation and no scare tactics, just the checks and rules of thumb professionals use on site, so you can talk to any contractor, including us, as an informed client.

{{ readLine }}

{{ countTxt }}

Loading the guides
We couldn’t load the guides.The connection may have dropped. Try again, or ask Delta below: its answers come from the same guides.
No guides match “{{ q }}”.Try a broader word such as damp, cement or RERA, or ask Delta below.
DID YOU KNOW · {{ factNo }}

{{ fact }}

These guides describe standard Indian construction practice and field checks aligned with IS codes, such as IS 456 for concrete, IS 383 for aggregates and IS 1893 for seismic zoning. They are general education. Every building is different, so treat anything structural as a reason for an on-site professional assessment, not a do-it-yourself diagnosis.

Ready to plan your own build?

Five taps give you a cost range, a season plan and your area’s rules. Or send us your plot for a free preliminary estimate, usually within 48 hours.*

Start your free estimate →Plan your build in five tapsTalk on WhatsApp

*Indicative, not guaranteed. Timing varies with the complexity of your query.

{{ g.dom }}· {{ g.mins }} MIN READ
{{ g.trNote }}

{{ g.title }}

{{ g.imgAlt }}
Photo: {{ g.imgBy }}, {{ g.imgLic }}, via Wikimedia Commons
THE SHORT ANSWER

{{ s.t }}{{ s.t }}

IN PLAIN WORDS

{{ s.t }}{{ s.t }}

{{ g.dNote }}

{{ s.t }}{{ s.t }}

{{ x.h }}

{{ s.t }}{{ s.t }}

  • {{ s.t }}{{ s.t }}
  1. {{ st.n }}{{ s.t }}{{ s.t }}
{{ r.label }}{{ c.k }}{{ c.v }}
{{ fg.alt }}
Photo: {{ fg.by }}, {{ fg.lic }}, via Wikimedia Commons

{{ x.h }}

{{ s.t }}{{ s.t }}

  • {{ s.t }}{{ s.t }}
  1. {{ st.n }}{{ s.t }}{{ s.t }}
{{ r.label }}{{ c.k }}{{ c.v }}

{{ g.faqT }}

{{ f.q }}

{{ s.t }}{{ s.t }}

RED FLAGS ON SITE
  • {{ s.t }}{{ s.t }}
PRO TIP

{{ s.t }}{{ s.t }}

SEEING THIS AT HOME?{{ g.probT }}Tick what you see and we tell you what it most likely means, with the fixes ranked honestly.Check yours → {{ g.goKick }}{{ g.goName }}{{ g.goDesc }}{{ g.goCta }} PLAY · ONE MINUTE{{ g.playName }}{{ g.playLine }}Play the game →
Ask our engineers on WhatsApp
{{ g.srcHead }}
  1. {{ s.l }}{{ s.chk }}

Checked against these sources on the dates shown, pending our team’s sign-off. Rules change, so we check them again for your plot before anything is filed.