How to read your structural drawings (GFC set)
You'll receive two families of drawings: architectural (what the building looks like and how spaces work) and structural (what holds it up — foundation, column, beam and slab details with bar sizes and spacing). 'GFC' means Good For Construction — the final, signed set the site must follow. The owner's job isn't to check the engineering; it's to confirm the site is building THIS set, at THIS revision, and nothing else.
Drawings are sheet music. You don't need to read every note — you need to confirm the orchestra is playing from the same, latest edition, not last month's draft.
A building is built twice: once on paper, then on site, and the site is only as good as the drawings it follows. For a house you will usually receive two families of drawings. Architectural drawings show the spaces: walls, doors, windows, levels and finishes. Structural drawings show what holds it all up: the foundations, columns, beams, slabs and stairs, with the size and position of every bar of steel.
You do not need to check the engineering. That is the structural engineer's job, and in Kolkata the rules make the professionals responsible for it. Your job, and your site supervisor's, is to make sure the site builds the right set, at the latest revision, exactly as drawn. This guide explains what is in a structural set, how to read its marks and notes, what Good For Construction means, how revisions are controlled, how to check the site against the drawings at each stage and what to keep at the end.
Two families of drawings, and the sanction
The architectural, structural and services drawings describe the same building from different sides, and they must agree. A beam that runs across a door head, a drain pipe that must pass through a beam, a bathroom slab that has to be sunk for the floor trap: each needs the drawings to match before the site reaches it. Most mistakes we find on site begin where two drawings disagree and someone on site picked one.
The sanctioned plan is something else again: the architectural plan the municipality approved. The working architectural drawings must match it, or the site is building a deviation from the day it starts. Our guide to reading your sanctioned plan explains what to compare.
| Set | What it shows | Who signs |
|---|---|---|
| Architectural | Rooms, walls, doors, windows, levels, finishes | The architect or licensed building surveyor |
| Structural | Foundations, columns, beams, slabs, stairs, steel | The structural engineer |
| Services | Water, drains, wiring and points | The services engineer or the architect |
| Sanctioned plan | What the municipality approved | Stamped by the municipality |
What a structural set contains
- General notes: the codes followed, the grades of concrete and steel, the covers, the lap and anchorage lengths, the safe bearing pressure assumed for the soil and any sequence of work.
- The foundation plan and details: footing or pile positions, sizes and depths, and the plinth beams.
- The column layout and schedule: every column on its grid position, with its size and steel at each floor.
- Beam layouts and details for each floor: each beam's size, top and bottom bars, extra bars at the supports, and its stirrups and their spacing.
- Slab layouts and details: thickness, bars in each direction, extra bars over supports, sunken areas and openings.
- The staircase, lintels, sunshades, the water tank and any retaining walls.
- The bar bending schedule: every bar's shape, length, number and weight; our guide to the bar bending schedule explains how to read it.
Reading the marks
Drawings use a shorthand. Grid lines run one way lettered and the other numbered, so every column has an address, and members carry marks that are listed in the schedules. Bars are written by number and diameter, spacings centre to centre, and levels against a fixed datum. Sections and details are called out with a circle giving the detail's number and the sheet it is drawn on, so you can follow a beam from the plan to its cross-section.
| Mark | Usually means |
|---|---|
| 4-16φ or 4 T16 | Four bars, each 16 mm in diameter |
| 10φ @ 150 c/c | 10 mm bars at 150 mm centre to centre |
| 2L-8φ @ 100 | Two-legged 8 mm stirrups at 100 mm |
| T and B | Top and bottom bars |
| FFL, SSL, TOS | Finished floor level, structural slab level, top of slab |
| F2, C1, B4, S3 | Footing, column, beam and slab marks, listed in the schedules |
| A circle with 3 over S-05 | Detail 3, drawn on sheet S-05 |
These are common conventions, not a rule every office follows. Each set's legend and general notes say how that engineer writes things; read those first.
What Good For Construction means
Drawings pass through stages: concept, for discussion, for approval by the owner or the municipality, and finally Good For Construction, the set the engineer signs and releases for the site to build from. Only GFC drawings should be on site. A sheet marked preliminary, for approval, for tender or not for construction must never be built from, however close it looks to the final one.
Each GFC sheet carries the project name, the sheet number and title, the engineer's signature or stamp, the date and the revision. If any of these is missing, ask before anything is built from it.
Revisions and the drawing register
Drawings change. The family moves a wall, the soil report arrives, a column clashes with a door. Each change gives a new revision, numbered R0, R1, R2 or lettered A, B, C, with a date, a line in the revision block saying what changed and often a cloud drawn round the change on the sheet. The older sheet is then superseded and must leave the site, or be stamped as superseded, the same day.
A drawing register lists every current sheet with its latest revision, and every issue of new drawings goes with a transmittal note saying which sheets were sent and to whom. On our sites one register lists every current sheet; it is the first thing to ask any contractor for.
- Ask for the drawing register: every sheet, its title and its latest revision.
- Compare the revision block on each sheet on site with the register.
- Remove superseded sheets, or stamp them clearly.
- Make sure the contractor, the bar bender and the supervisor work from the same prints, not from phone photographs.
- When something has to change on site, get a revised drawing or a signed sketch from the engineer before the work is done.
Checking the site against the drawings
An owner, or an owner's supervisor, can check a great deal without doing any engineering, simply by comparing what is on site with what is on the sheet at the moments before it is hidden. Our Lap & Development Length calculator shows how lap lengths are worked out, and why a lap on site must be as long as the drawing says.
| Stage | Check against the drawings |
|---|---|
| Setting out | Grid lines and column positions match the column layout; the building sits on the plot as the site plan shows |
| Footings | Sizes, depths and bars, before the concrete |
| Columns | Size, the number and size of bars, the ties and their spacing, laps where the drawing puts them |
| Beams and slabs | Beam sizes, extra bars at supports, slab thickness, bars and spacing, sunken areas and openings |
| Before every pour | Cover blocks in place, sleeves and conduits fixed, the check signed |
| Stairs, lintels, sunshades | Thickness, bars and their bearing on walls and beams |

Common mismatches we find
- A site working from an old revision, or a phone photograph of one.
- Smaller bars, or fewer bars, than the schedule asks for.
- Stirrups spaced wider than drawn, especially near the ends of beams and columns, where the drawing closes them up.
- Laps all at one level, or in the part of a beam or column where the drawing does not allow them.
- A column moved a little to suit a door or the neighbour's wall, without the engineer.
- A slab thinner than drawn, or a sunken bathroom slab cast flat.
- Holes cut through beams for pipes that were never on the drawings.
- Adjusted at site, with no revised drawing to show for it.
Who is responsible
The structural engineer is responsible for the design. Inside Kolkata, the KMC Building Rules make the professionals who plan, design and supervise a building jointly and severally responsible for the safety of its structure; a building above 10 m, or with piles or a basement, must have a structural engineer (rule 47), and a structural stability certificate goes in with the notice of completion (rule 27). In the municipalities, the engineers must be empanelled with that municipality.
The contractor is responsible for building what is drawn, and the supervisor for checking it. When something on site cannot be built as drawn, the answer is a question to the engineer, not an adjustment by the mason.
At the end: as-built drawings
Buildings rarely end exactly as first drawn. Ask for an as-built set at handover: the final drawings with every change made during construction, signed. Keep it with the property papers, together with the soil report, the bar bending schedules and the test reports. It is what an engineer will need years later for a renovation, a repair, an assessment or an extra floor; our guide to adding a floor explains why.
The 5 things an owner should locate
- The revision block: number and date — every drawing on site must match the latest revision.
- The 'GFC' stamp — draft or 'for approval' sets must never be built from.
- Column layout sheet — count and positions should match what's marked out on site.
- Bar bending schedule — the steel list your bills should reconcile against.
- Notes on concrete grade and cover — the two specs most often quietly downgraded.
Questions people ask
Do you need to understand the engineering in the drawings?
No. The engineer is responsible for the design. Your part is to make sure the site builds the current GFC set exactly as drawn, and to ask whenever something on site differs from the sheet.
What does GFC mean on a drawing?
Good For Construction: the final, signed set released for the site to build from. Sheets marked preliminary, for approval or not for construction must never be built from.
How can you tell whether a drawing is the latest?
Check its revision block against the drawing register, which lists every sheet with its latest revision. Old sheets should be taken off site or stamped as superseded.
Can the contractor swap a bar size that is not available?
Only with the engineer's written approval and a revised drawing or a signed note. A different bar size changes the steel area, the spacing and the laps, which is the engineer's decision.
Are the sanctioned plan and the structural drawings the same?
No. The sanctioned plan is the architectural plan the municipality approved; the structural drawings show how the building is held up. They must agree, and the working architectural drawings must match the sanction.
What should you keep after the build?
The as-built architectural and structural drawings, the soil report, the bar bending schedules, the test reports and the engineers' certificates. Every future repair, extension or assessment starts from them.
Red flags
- Site working from a WhatsApp photo of an old drawing
- Two different revisions of the same sheet floating on site
- 'We adjusted it at site' with no revised drawing to show
Pro tip
On Delta sites, one register lists every current GFC sheet and revision — ask any contractor for the same register. Hesitation is information.
Work it out: Lap & Development Length
Sources
- IS 456:2000 Plain and Reinforced Concrete, Code of Practice (Bureau of Indian Standards) (checked 15 Nov 2026)
- SP 34:1987 Handbook on Concrete Reinforcement and Detailing (Bureau of Indian Standards) (checked 15 Nov 2026)
- IS 962:1989 Code of Practice for Architectural and Building Drawings (Bureau of Indian Standards) (checked 15 Nov 2026)
- KMC Building Rules, 2009, consolidated to 23 Dec 2019 (Indian Kanoon) (checked 14 Oct 2026)
Checked against these sources on the dates shown, pending our team’s sign-off.