Metro and flyover works in Kolkata: which roads, and how long

Where each line stands in mid-November 2026, which roads stay barricaded, and what changes if you build or live beside the works.

By Raj Sekhar Ghosh, Editor. Published 2026-11-20.

The Orange Line viaduct above the Major Arterial Road at Chinar Park, with barricades along the road
The Orange Line viaduct at Chinar Park, on the stretch towards the airport that is still being built (photographed September 2023). Photo: খাঁ শুভেন্দু, CC BY-SA 4.0, via Wikimedia Commons

Key points

  • Orange Line: trains have run on trial between Beleghata and IT Centre (Sector V) since 10 October. Metro and RVNL are aiming for passenger services in December, after the safety commissioner's inspection.
  • Purple Line: both tunnels from Khidderpore to Victoria are bored (July and August 2026). Trains still run only between Joka and Majerhat.
  • Yellow Line: Noapara to the airport has run since August 2025. The stretches to New Barrackpore and Barasat are still being built.
  • Blue Line: trains turn back at Shahid Khudiram while the Kavi Subhash station complex is rebuilt.
  • The EM Bypass to New Town flyover waits on a cost review before a fresh tender. The Chingrighata flyover stays in use.
  • Within up to 20 metres of a metro alignment, the central government can bar or regulate building. Check your plot before you plan.

Orange Line: Sector V is next

The Orange Line runs 9.9 km along the EM Bypass from Kavi Subhash (New Garia) to Beleghata. The first part, to Hemanta Mukhopadhyay at Ruby, opened in March 2024, and the extension to Beleghata in August 2025.

Trial runs on the next 4.5 km, from Beleghata to IT Centre in Salt Lake Sector V, began on 10 October 2026. The stretch adds three stations: Gour Kishore Ghosh at Chingrighata, Nalban and IT Centre. The Commissioner of Railway Safety still has to inspect and clear it; Metro Railway and RVNL have said they are aiming for December, and on 20 November officials told PTI the stretch is likely to open by the end of the year.

At Sector V a footbridge will link the Orange Line's IT Centre station with the Green Line's Sector V station, so you can change lines without crossing the road.

Beyond IT Centre, the line towards City Centre-2, New Town and the airport is still under construction, in phases with no firm opening date. Expect the barricades along the Major Arterial Road and around Chinar Park to stay through 2027.

Purple Line: tunnels done to Victoria

Trains run on the elevated 7.75 km from Joka to Majerhat. From Mominpur the line goes underground, under Khidderpore Road and J L Nehru Road, to Esplanade.

Tunnel boring machine Durga broke through at Victoria on 10 July 2026, and its sister machine Divya finished the second tube on 11 August. Each drive was about 1.72 km from the shaft at Khidderpore.

The work now moves to the stations (Khidderpore, Victoria, Park Street and Esplanade), then track and signalling. The tunnels on from Victoria to Park Street, about 950 m, were planned to be finished by the end of 2026, and the last 500 m to Esplanade is being built by cut and cover. No date has been announced for trains beyond Majerhat. Expect station works and diversions on these roads for some time. When the line is finished, Esplanade becomes a three-line interchange: Blue, Green and Purple.

Metro viaducts of the Green Line and the Orange Line under construction in Salt Lake Sector V
The Green Line (left) and the Orange Line under construction in Sector V, where the two will be linked by a footbridge (photographed November 2017). Photo: SomsubhroK, CC BY-SA 4.0, via Wikimedia Commons

Yellow Line: the airport is open, the north is still building

The 7.04 km from Noapara to Jai Hind, the airport station, opened on 22 August 2025 and is the city's first direct metro to the airport.

Extensions towards New Barrackpore and Barasat are under construction. The stretch to Barasat has been held up for years by encroachments and land, so plan any build along Jessore Road beyond the airport around continuing works.

Blue Line: Kavi Subhash is being rebuilt

Services to Kavi Subhash stopped on 28 July 2025 after cracks were found in the station's supporting piers. Metro decided to pull down the Blue Line station complex and rebuild it, keeping the tracks, and Blue Line trains now turn back at Shahid Khudiram.

In October 2025 Metro estimated six to seven months of work once it began, with services back by mid-2026. As we check this in mid-November 2026, the Blue Line still ends at Shahid Khudiram. Orange Line trains are not affected.

Flyovers: the EM Bypass to New Town link

KMDA's planned four-lane flyover would run about 7 km from Metropolitan on the EM Bypass, over Chingrighata and Sector V, to Mahishbathan in New Town. It is meant to replace the ageing Chingrighata flyover.

KMDA invited bids in November 2025 on an estimate of ₹666 crore. The only bid, from L&T, was close to ₹900 crore, so the state asked RITES to review the cost before a fresh tender. There is no start date yet, and the Chingrighata flyover stays in use until a new one is built.

Building or living beside the works

Section 21 of the Metro Railways (Construction of Works) Act, 1978 lets the central government, by notification, bar or regulate building above a metro alignment and on land within up to 20 metres on either side of it. It can also order alterations to an existing building there, or a temporary evacuation while works go on.

Before you buy, rebuild or add floors on a plot near an alignment, ask Metro Railway and your municipal building department whether a notified band covers it, and whether your plan needs Metro's no-objection letter.

If you live in an older house next to tunnelling, piling or viaduct work, photograph and date every crack you can see now, inside and out, and keep the record. If new cracks appear, it is the evidence you will need.

What this means for you

  • Starting a build near the EM Bypass, Salt Lake or New Town: plan for barricaded roads and narrow access into 2027, and ask your contractor how materials will reach the site.
  • Buying land near a metro line: check the alignment and any notified band before you pay.
  • Living next to the works: record your house's condition now, with dated photographs.
  • Renovating near Diamond Harbour Road or Khidderpore Road: expect station works and diversions for some time.

Sources

  1. Metro Rail News (PTI): the Beleghata–Sector V stretch likely to open by year-end, awaiting CRS clearance (20 November 2026) (checked 2026-11-22)
  2. Construction World: Kolkata Metro's 4.5 km Beleghata–IT Centre corridor eyes December opening (Oct 2026) (checked 2026-11-15)
  3. Construction World: Orange Line trial runs to Sector V from 10 October (Sep 2026) (checked 2026-11-15)
  4. Metro Rail News: Kolkata Metro Orange Line route, stations and status (checked 2026-11-15)
  5. Metro Rail News: Kolkata Metro Purple Line route, stations and status (Oct 2026) (checked 2026-11-20)
  6. Swarajya: TBM Divya breaks through at Victoria station (12 Aug 2026) (checked 2026-11-15)
  7. Construction World: Purple Line tunnel breakthrough (14 Aug 2026) (checked 2026-11-15)
  8. Millennium Post: Kavi Subhash Metro station reconstruction to begin soon (Oct 2025) (checked 2026-11-15)
  9. Swarajya: independent cost review for the New Town–Metropolitan flyover (2026) (checked 2026-11-15)
  10. The Metro Railways (Construction of Works) Act, 1978, section 21 (checked 2026-11-15)
  11. Metro Railway, Kolkata (official site) (checked 2026-11-15)

Check it yourself

Skip to content

We can’t find that article.

It may have moved, or it is not published yet.

All news
DRAFT · NOT PUBLISHED{{ draftLine }}
  1. {{ c }}
{{ catUp }}· {{ mins }}

{{ t }}

{{ dek }}

By Raj Sekhar Ghosh, Editor{{ dateLine }}
Share on WhatsApp

Copying is blocked here. Select the link and copy it: {{ shareU }}

{{ alt }}
{{ cap }} Photo: {{ img.by }}, Wikimedia Commons, {{ img.lic }}.

{{ kpTitle }}

  • {{ k }}

পুরো লেখার বাংলা অনুবাদ রাজ শেখর ঘোষের অনুমোদনের পর ইংরেজির সঙ্গে একই দিনে প্রকাশিত হবে। নিচের অংশ এখন ইংরেজিতে।

{{ s.h }}

{{ p }}

{{ s.fig.alt }}
{{ s.fig.cap }} Photo: {{ s.fig.by }}, Wikimedia Commons, {{ s.fig.lic }}.

{{ youTitle }}

  • {{ y }}
Ask us about this on WhatsApp

Sources

{{ updLine }}

  1. {{ r.n }} · checked {{ r.c }}

We update this article when a date or a fact changes, and say what changed.

Check it yourself

FROM DELTA STRUCTURES, WHO PUBLISH NEWS

{{ endH }}

{{ endP }}